Vitali Retng Wall (Dupa Format)

download Vitali Retng Wall (Dupa Format)

of 61

Transcript of Vitali Retng Wall (Dupa Format)

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    1/61

    Project : Proposed Construction of Concrete Retaining Wall at Tamion Production WellLocation : Lower Tamion, Vitali, Zamboanga City

    Scope of Works : Construction of 30.00 Linear Meters of Concrete Retaining Wall

    A. NON- ENGINEERING BASIC ITEMSA. SUPERVISIONB. CONSTRUCTION OF TEMPORARY FACILITIES

    B. ENGINEERING BASIC ITEMSI. MOBILIZATION/HAULING OF MATERIALSII. DEMOLITION OF EXISTING 28.00 LINEAR METERS RIP-RAPIII. DIVERSION WORKSIV. EXCAVATION WORKS

    V. LAY-OUTING WORKSVI. CONCRETING WORKSVII. FORMS & SCAFFOLDING WORKS

    VIII. REBAR WORKSIX. DEMOBILIZATION/BACKFILL WORKS

    Cost of Project :

    Qty Unit Unit Cost Sub - Total Total

    A. NON- ENGINEERING BASIC ITEMS

    A. SUPERVISION1 - Engineering Assistant 100 days 542.00 54,200.00 54,200.00

    Direct Cost 54,200.00OCM 5,438.00Total Cost of Item A 59,638.00

    B. CONSTRUCTION OF TEMP. FACILITIES (Area = 3.00mtrs. X 5.00mtrs., 1 - Unit)

    A. Materials26 pcs. - 2" x 4" x 10' Coco Lumber 173 bd.ft. 20.00 3,460.00

    18 pcs. - 2" x 3" x 10' Coco Lumber 90 bd.ft. 20.00 1,800.0016 pcs. - 2" x 2" x 10' Coco Lumber 53 bd.ft. 20.00 1,060.00

    * 12mm thk x 1.20m x 2.40m Ordinary Plywood 18 shts. 975.00 17,550.00

    Gauge 26 x 1.80m Length Corrugated G.I. Roofing Sheets 18 shts. 221.00 3,978.00

    Gauge 26 x 1.20m x 2.40m G.I. Plain Sheet 1 sht. 425.00 425.002" C.W. Nail 2 kgs. 65.00 130.003" C.W. Nail 1 kg. 70.00 70.004" C.W. Nail 2 kg. 70.00 140.00

    Padlock (Big) 1 pc. 150.00 150.003-1/2" Loose Pin Hinges 3 pairs 45.00 135.001/8" G.I. Chain (1Kg. Equal to 2mtrs.) 1 kg. 163.00 163.002" C.W. Umbrella Roofing Nails 2 kgs. 92.00 184.00 29,245.00

    B. Labor:

    2 - Carpenters 6 days 366.00 4,392.00

    4 - Laborers 6 days 317.00 7,608.00 12,000.0041,245.00

    B. ENGINEERING BASIC ITEMSI. MOBILIZATION/HAULING OF MATERIALS

    A. Equipment Rental

    1 - Unit Boom Truck (w/Driver) 14 days 5,500.00 77,000.00Diesel Fuel 2,800 liters 49.00 137,200.00 214,200.00

    B. Labor

    4 - Laborers 14 days 317.00 17,752.00 17,752.00Direct Cost 231,952.00

    OCM 23,808.00

    Republic of the Philippines

    ZAMBOANGA CITY WATER DISTRICTPilar Street, Zamboanga City

    Php2,218,094.00

    BILL OF MATERIALS AND COST ESTIMATE

    Item Description

    1/3Pricelist Database as of Feb. - March, 20

    Construction Equipment Rental Rates Based on ACEL Equipment Guidebook 2009, Edition 24 (AS OF March 201

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    2/61

    Total Cost of Item I 255,760.00

    II. DEMOLITION OF EXISTING 28.00 LINEAR METERS RIP-RAP

    A. Labor2 - Carpenters 12 days 366.00 8,784.00

    4 - Masons 12 days 366.00 17,568.004 - Steelmans 12 days 366.00 17,568.00

    12 - Laborers 12 days 317.00 45,648.00 89,568.00

    2/3Pricelist Database as of Feb. - March, 20

    Construction Equipment Rental Rates Based on ACEL Equipment Guidebook 2009, Edition 24 (AS OF March 201

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    3/61

    B. Equipment Rental/Fuel:

    1 - Compressor w/ Jackhammer (w/ Operator) 12 days 8,000.00 96,000.00Diesel Fuel 96 ltrs. 49.00 4,704.00 100,704.00Direct Cost 190,272.00OCM 19,640.00Total Cost of Item II 209,912.00

    III. DIVERSION WORKS

    Note: Diversion the flow of water from river.

    A. Labor:12 - Laborers 13 days 317.00 49,452.00 49,452.00

    B. Equipment Rental/Fuel:

    1 - Water Pump 12 days 500.00 6,000.00Premium Gasoline 48 liters 60.00 2,880.00 8,880.00Direct Cost 58,332.00OCM 6,446.00Total Cost of Item III 64,778.00

    IV. EXCAVATION WORKS

    Note: Excavation only for base foundation.

    24 - Laborers 6 days 317.00 45,648.00 45,648.00Direct Cost 45,648.00OCM 4,565.00Total Cost of Item IV 50,213.00

    V. LAY-OUTING WORKS

    A. Labor:

    2 - Carpenters 1 day 366.00 732.00 732.00Direct Cost 732.00OCM 73.00Total Cost of Item V 805.00

    VI. CONCRETING WORKS

    A. Materials:

    Concrete 1,040.00Portland Cement 1,352.00 1,352 bags 260.00 351,520.00Washed Sand 57 cu.m. 1,000.00 57,000.00Gravel (G-1) 75 cu.m. 1,000.00 75,000.0075mm x 3.00m PVC Pipe, Series 1,000 8 pcs. 563.00 4,504.00 488,024.00

    B. Labor:

    2 - Carpenters 27 days 366.00 19,764.004 - Masons 27 days 366.00 39,528.004 - Steelmans 27 days 366.00 39,528.00

    12 - Laborers 27 days 317.00 102,708.00 201,528.00

    C. Equipment Rental/Fuel:

    1 - Unit Concrete Bagger Mixer 27 days 1,500.00 40,500.001 - Concrete Vibrator 27 days 500.00 13,500.00

    Special Gasoline 414 liters 60.00 24,840.00 78,840.00Direct Cost 768,392.00OCM 77,452.00Total Cost Item IV 845,844.00

    VII. FORMS & SCAFFOLDING WORKS

    A. Materials:130 130pcs. - 2" x 4" x 10' Coco Lumber 867 bd.ft. 20.00 17,340.0096 96pcs. - 2" x 3" x 10' Coco Lumber 480 bd.ft. 20.00 9,600.0060 * 12mm thk x 1.20m x 2.40m Ordinary Plywood 60 shts. 975.00 58,500.00

    270pcs. - 2" x 3" x 8' Coco Lumber 1,080 bd.ft. 20.00 21,600.00124 2" C.W. Nail 15 kgs. 65.00 975.00270 4" C.W. Nail 36 kgs. 70.00 2,520.00 110,535.00

    B. Labor:

    2 - Carpenter 21 days 366.00 15,372.004 - Laborers 21 days 317.00 26,628.00 42,000.00

    Direct Cost 152,535.00OCM 15,867.00

    3/3 Pricelist Database as of Feb. - March, 201Construction Equipment Rental Rates Based on ACEL Equipment Guidebook 2009, Edition 24 (AS OF March 2012

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    4/61

    Total Cost Item V 168,402.00

    VIII REBAR WORKS A. Materials:

    16mm x 6.00m Def. Reinforcing Steel Bar 449 pcs. 450.00 202,050.00

    12mm x 7.50m Def. Reinforcing Steel Bar 120 pcs. 344.00 41,280.0012mm x 6.00m Def. Reinforcing Steel Bar 491 pcs. 250.00 122,750.00

    Hacksaw Blade 12 pcs. 72.00 864.00#16 G.I. Tie-wire 143 kgs. 75.00 10,725.00 377,669.00

    B. Labor:

    4 - Steelmans 24 days 366.00 35,136.004 - Laborers 24 days 317.00 30,432.00 65,568.00

    4/3Pricelist Database as of Feb. - March, 20

    Construction Equipment Rental Rates Based on ACEL Equipment Guidebook 2009, Edition 24 (AS OF March 201

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    5/61

    C. Equipment Rental1 - Unit Bar Cutter 24 days 300.00 7,200.00 7,200.00

    Direct Cost 450,437.00

    OCM 45,657.00Total Cost Item VI 496,094.00

    IX. DEMOBILIZATION/BACKFILL WORKSA. Labor:

    2 - Carpenters 2 days 366.00 1,464.00

    4 - Masons 2 days 366.00 2,928.004 - Steelmans 2 days 366.00 2,928.0024 - Laborers 2 days 317.00 15,216.00 22,536.00

    Direct Cost 22,536.00OCM 2,867.00Total Cost Item VII 25,403.00

    Sizing RequirementsNote: * All sizes referred herein should mean commercially available measurements with tolerance of + 1mm.

    A. NON- ENGINEERING BASIC ITEMSA. SUPERVISIONB. CONSTRUCTION OF TEMPORARY FACILITIES

    B. ENGINEERING BASIC ITEMS

    I. MOBILIZATION/HAULING OF MATERIALSII. DEMOLITION OF EXISTING 28.00 LINEAR METERS RIP-RAPIII. DIVERSION WORKSIV. EXCAVATION WORKS

    V. LAY-OUTING WORKSVI. CONCRETING WORKSVII. FORMS & SCAFFOLDING WORKSVIII REBAR WORKSIX. DEMOBILIZATION/BACKFILL WORKS

    Prepared by: Reviewed & Checked by: Approved by:

    FELIXBERTO R. CAARE, JR. MARIE CLAIRE C. BONGO EFREN C. SALVACIONResearcher/Analyst A, (J.O.) Principal Engineer C Division Manager CPlanning & Development Section Planning & Development Section Planning & Design Division

    Recommending Project Implementation: Approved for Project Implementation:

    ARNULFO A. ALFONSO LEONARDO REY D. VASQUEZ

    Department Manager C, Maintenance Dept. General Manager

    Concurrent Head, Engineering

    168,402.00PhP

    2,218,094.00PhP

    S U M M A R Y

    59,638.00PhP41,245.00PhP

    496,094.00PhP

    50,213.00PhP805.00PhP

    25,403.00PhP

    255,760.00PhP209,912.00PhP

    64,778.00PhP

    845,844.00PhP

    5/3 Pricelist Database as of Feb. - March, 201Construction Equipment Rental Rates Based on ACEL Equipment Guidebook 2009, Edition 24 (AS OF March 201

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    6/61

    PROJECT : PROPOSED CONSTRUCTION OF CONCRETE RETAINING WALL AT TAMION PRODUCTION W

    Location : Lower Tamion, Vitali, Zamboanga City

    Project Cost :Project Duration : ONE HUNDRED(100)CALENDARDAYS

    Manpower Requirements : 35 MANPOWER(1-Engineering Assistant, 24-Laborers, 4-Steelman, 2-Carpenters, & 4-Masons)

    13 DAYS

    1 DAY

    6 DAYS 6 DAYS 14 D

    12 DAYS

    14 DAYS

    c f&c r

    A - Construction of temporary facilities NON -

    B - Hauling of materials/ Mobilization A. SUP

    C - Divertion Works (Divert direction of water flow from river) B. CON

    D - Demolition of existing riprap ENGIN

    E - Lay - outing works I. MOB

    F - Excavation for Base Foundation II. DEM

    G - Fabrication and installation of steel bar for base foundation 14 III. DIV

    H - Concrete pouring on base foundation 9 IV. EXC

    I - Fabrication and installation of steel bar for first lift 2 V. LAY

    J - Fabrication and installation of forms and scaffolding 5 VI. CO

    K - Concrete pouring on first lift 4 VII. FO

    L - Fabrication and installation of steel bar for second lift 2 VIII. R

    M - Fabrication and installation of forms and scaffolding 5 IX. DE

    N - Concrete pouring on second lift 4

    O - Fabrication and installation of steel bar for third lift 2

    P - Fabrication and installation of forms and scaffolding 4

    Q - Concrete pouring on third lift 4

    R - Fabrication and installation of steel bar for fourth lift 2

    S - Installation of weepholes

    T - Fabrication and installation of forms and scaffolding 4

    U - Concrete pouring on fourth lift 3

    V - Fabrication and installation of steel bar for fifth lift 2

    W - Installation of weepholes

    X - Fabrication and installation of forms and scaffolding 3

    Y - Concrete pouring on fifth lift 3

    Z - Installation of granular gravel filter

    A' - Demobilization/ Backfill

    27 21 24

    2 Y, Z

    3 V, W

    3 X

    1 Y

    3 T

    2 U

    2 U

    2 Q

    2 Q

    4 R, S

    2 N

    4 O

    4 P

    2 K

    5 L

    4 M

    5 I

    4 J

    9 G

    2 H

    6 B, E

    14 F

    12 A

    1 C, D

    13 A

    6

    14

    ACTIVITY COMPLETED DURATION(DAYS) PRECEDENCE

    PERT CPM

    2,218,094.00PhP

    A

    C

    STAR

    T

    D

    E F

    B

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    7/61

    PROJECT : Proposed Construction of Concrete Retaining Wall at Tamion Production WellLocation : Lower Tamion, Vitali, Zamboanga City

    Project Cost :Project Duration : ONE HUNDRED (100) CALENDAR DAYS

    Manpower Requirements : 35 Manpower (1-Engineering Assistant, 24-Laborers, 4-Steelman, 2-Carpenters, & 4-Masons)

    A. NON- ENGINEERING BASIC ITEMSA. SUPERVISION 2.69% # # # # # # # # # # # # # # # # #

    B. Construction of Temp. Facilities 1.86%B. ENGINEERING BASIC ITEMS 0.00%

    I. MOBILIZATION/HAULING OF MATERIALS 11.53% # # # # # # # # # # # # # #II. DEMOLITION OF EXISTING 28.00 LINEAR METERS RIP-RAP 9.46% # # # # # # # # # #

    III. DIVERSION WORKS 2.92%IV. EXCAVATION WORKS 2.26%

    V. LAY-OUTING WORKS 0.04%VI. CONCRETING WORKS 38.13%

    VII. FORMS & SCAFFOLDING WORKS 7.59%VIII. REBAR WORKS 22.37%

    IX. DEMOBILIZATION/BACKFILL WORKS 1.15%

    TOTAL PROJECT COST 100%

    CASH OUTLAY REQUIREMENT

    TARGETED COMPLETION THIS PERIOD

    COMMULATIVE COMPLETION TO DATE

    Prepared by: Reviewed & Checked by: Approved by:

    FELIXBERTO R. CAARE, JR. MARIE CLAIRE C. BONGO EFREN C. SALVResearcher/Analyst A (J.O.) Principal Engineer C Division Manage

    Planning & Development Section Planning & Development Section Planning & Desi

    845,844.00Php

    168,402.00Php496,094.00Php

    36.

    209,912.00Php

    808,3

    36.

    ZAM

    64,778.00Php50,213.00Php

    805.00Php

    255,760.00Php

    41,245.00Php59,638.00Php

    25,403.00Php

    2,218,094.00Php

    GANTT CHART

    2,218,094.00Php

    Work Item Amounts Percent

    Perfected3

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    8/61

    PROJECT NAME:

    Item No./Description: Construction of Temporary Facilities

    Unit of Measurement:

    Output per day:

    Quantity:

    A. Labor

    a. Construction Foreman/Eng'g Assist.

    b. Skilled Laborer

    c. Laborer

    B. Equipment

    N/A

    C.

    D. Output per day =

    E. Materials

    a.

    b.

    c.

    d.

    e.

    f. Ga. 26 x 1.20m x 2.40m G.I. Plain Sheet

    g. 2" C.W. Nail

    DETAILED UNIT PRICE ANALYSIS

    PROP. CONSTRUCTION OF CONCRETE RETAINING WALL AT TAMI

    SPL-1

    lot

    1.00 lot

    2 6 36

    4 6 31

    Designation No. Person No. of Days Dail

    1 6 52

    Sub-Total for A

    Name and Capacity No. of Units No. of Days Dail

    Sub-Total for B

    Total (A+B)

    Name and Specifications Quantity Unit Uni

    12mm thk x 1.20m x 2.40m Ordinary

    Plywood

    18 shts. 97

    Ga. 26 x 1.80m Length Corrugated G.I.

    Roofing Sheet

    18 shts. 22

    8,5

    16 pcs. - 2" x 2" x 10' Coco Lumber 0.12506

    26 pcs. - 2" x 4" x 10' Coco Lumber 0.40823 cu.m. 8,5

    18 pcs. - 2" x 3" x 10' Coco Lumber 0.21237 cu.m.

    sht. 42

    2 kgs. 6

    cu.m. 8,5

    1

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    9/61

    h. 3" C.W. Nail

    i.

    j.

    k. 3-1/2" Loose Pin Hinges

    l. 1/8" G.I. Chain (1kg. Equal to 2mtrs.)

    m. 2" C.W. Umbrella Roofing Nails

    F. Direct Cost (C+E)

    G. Overhead, Contingencies & Miscellaneous 0% per D.O. 29 s

    H. Contractor's Profit (CP) 0% per D.O. 29 s

    I. Value Added Tax (VAT) 0% per D.O. 29 s

    J. Total Cost

    k. Total Unit Cost

    PROJECT NAME:

    Item No./Description: Demolition of existing Rip-rap

    Unit of Measurement:

    Output per day: ln.m. /day

    Quantity:

    A. Labor

    a. Construction Foreman/Eng'g Assist.

    b. Skilled Laborer

    c. Laborer

    B. Equipment

    a. Compressor w/ Jackhammer

    C.

    4" C.W. Nail 2 kgs. 7

    Padlock (Big) 1 pc. 15

    Sub-Total for E

    3 pairs 4

    1 12 52

    2.33

    28.00 ln.m.

    Designation No. Person No. of Days

    DETAILED UNIT PRICE ANALYSIS

    PROP. CONSTRUCTION OF CONCRETE RETAINING WALL AT TAMI

    SPL-2

    ln.m.

    Dail

    Name and Capacity No. of Units No. of Days Dail

    12 days 10,4

    Sub-Total for A

    10 12 36

    12 12 31

    Sub-Total for B

    Total (A+B)

    7

    16

    9

    1

    1

    2

    kg.

    kg.

    kgs.

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    10/61

    D. Output per day = ln.m.

    E. Material

    N/A

    F. Direct Cost (C+E)

    G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s

    H. Contractor's Profit (CP) 0% per D.O. 29 s

    I. Value Added Tax (VAT) 0% per D.O. 29 s

    J. Total Costk. Total Unit Cost

    PROJECT NAME:

    Item No./Description: SPL-3 Diversion Works

    Unit of Measurement:

    Output per day:Quantity:

    A. Labor

    a. Construction Foreman/Eng'g Assist.

    b. Laborer

    B. Equipment

    a. Water Pump

    2.33

    Name and Specifications Quantity Unit Uni

    Sub-Total for E

    1 13 52

    1.00 lot

    Designation No. Person No. of Days Dail

    DETAILED UNIT PRICE ANALYSIS

    PROP. CONSTRUCTION OF CONCRETE RETAINING WALL AT TAMI

    lot

    Name and Capacity No. of Units No. of Days Dail

    1 12 98

    Sub-Total for A

    12 13 31

    Sub-Total for B

    /day

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    11/61

    C.

    D. Output per day =

    E. Materials

    N/A

    F. Direct Cost (C+E)

    G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s

    H. Contractor's Profit (CP) 0% per D.O. 29 s

    I. Value Added Tax (VAT) 0% per D.O. 29 s

    J. Total Cost

    k. Total Unit Cost

    PROJECT NAME:

    Item No./Description: Reinforcing Steel Bar, Grade 40

    Unit of Measurement:

    Output per day: kg./ day

    Quantity:

    A. Labor

    a. Construction Foreman/Eng'g Assist.

    b. Skilled Laborer

    c. Laborer

    B. Equipment

    a. Bar Cutter

    b. Bar Bender

    c. Cargo Truck (10T, 270Hp)

    Total (A+B)

    Name and Specifications Quantity Unit Uni

    Sub-Total for E

    1 6 52

    1,440.00

    7,668.26 kg.

    Designation No. Person No. of Days

    DETAILED UNIT PRICE ANALYSIS

    PROP. CONSTRUCTION OF CONCRETE RETAINING WALL AT TAMI

    404(2)

    kg.

    2 6 36

    8 6 31

    Dail

    1 1.20 8,8

    1 2 1,7

    1 2 2,8

    Sub-Total for A

    Name and Capacity No. of Units No. of Days Dail

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    12/61

    C.

    D. Output per day = kg./ day

    E. Materials

    a.

    b.

    c.

    d.

    e.

    F. Direct Cost (C+E)

    G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s

    H. Contractor's Profit (CP) 0% per D.O. 29 s

    I. Value Added Tax (VAT) 0% per D.O. 29 s

    J. Total Cost

    k. Total Unit Cost

    PROJECT NAME:

    Item No./Description: Lay-out and Excavation

    Unit of Measurement:

    Output per day: cu.m. /day

    Quantity:

    A. Labor

    a. Construction Foreman/Eng'g Assist.

    b. Skilled Laborer

    c. Laborer

    4,252.03 kgs. 4

    12mm.x 7.50m. Def. Reinforcing Steel

    Bar

    799.20 kgs. 51

    Sub-Total for B

    Total (A+B)

    1,440.00

    Name and Specifications Quantity Unit Uni

    16mm.x 6.00m. Def. Reinforcing Steel

    Bar

    Sub-Total for E

    143 kgs. 75

    No. of Days Dail

    1 4 52

    cu.m.

    32.00

    109.87 cu.m.

    Designation No. Person

    DETAILED UNIT PRICE ANALYSIS

    PROP. CONSTRUCTION OF CONCRETE RETAINING WALL AT TAMI

    103(1)a

    2 4 36

    10 4 31

    Hacksaw Blade 12 pcs. 72

    #16 G.I. Tie-Wire

    12mm.x 7.50m. Def. Reinforcing Steel

    Bar

    2,617.03 kgs. 46

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    13/61

    B. Equipment

    a. Dump Truck (10 cu.m.)

    b. Backhoe w/ Breaker (0.80 cu.m.)

    Minor Tools (10% of Labor)

    C.

    D. Output per day = cu.m. /day

    E. Materials

    N/A

    F. Direct Cost (C+E)

    G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s

    H. Contractor's Profit (CP) 0% per D.O. 29 s

    I. Value Added Tax (VAT) 0% per D.O. 29 s

    J. Total Cost

    k. Total Unit Cost

    PROJECT NAME:

    Item No./Description: Structural Concrete

    Unit of Measurement:

    Output per day: cu.m. /day

    Quantity:

    1 3 12,2

    Sub-Total for A

    Name and Capacity No. of Units No. of Days Dail

    Total (A+B)

    32.00

    Name and Specifications Quantity Unit Uni

    Sub-Total for B

    2 3 10,8

    Sub-Total for E

    22.40

    135.20 cu.m.

    DETAILED UNIT PRICE ANALYSIS

    PROP. CONSTRUCTION OF CONCRETE RETAINING WALL AT TAMI

    405

    cu.m.

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    14/61

    A. Labor

    a. Construction Foreman/Eng'g Assist.

    b. Skilled Laborer

    c. Laborer

    Installation of Formworks

    a. Skilled Laborer

    b. Laborer

    B. Equipment

    a. One Concrete Bagger Mixerb. Concrete Vibrator

    c. Water Truck (1000 gal.)

    C.

    D. Output per day = cu.m. /day

    E. Materials

    a.

    b.

    c.

    d.

    F. Direct Cost (C+E)

    G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s

    1 6 52

    . .

    8 6 31

    4 6 36

    8 6 36

    16 6 31

    1 6.00 8,5

    2 6.00 1,32 6.00 97

    Sub-Total for A

    Name and Capacity No. of Units No. of Days Dail

    Washed Sand 57 cu.m. 90

    Gravel (G-1) 75 cu.m. 90

    Portland Cement 1,352 bags 26

    Sub-Total for B

    Total (A+B)

    22.40

    Name and Specifications Quantity Unit Uni

    270pcs. - 2" x 3" x 8' Coco Lumber 2.54851 cu.m. 8,51

    12mm. Thk. X 1.20m. X 2.40m. Ordinary

    Plywood

    60 shts. 97

    Forms

    41pcs. - 2" x 4" x 10' Coco Lumber 0.64420 cu.m. 8,51

    75mm.x 3.00m. PVC Pipe, Series 1000 8 pcs. 56

    Sub-Total for E

    2" C.W. Nail 15 kgs. 65

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    15/61

    H. Contractor's Profit (CP) 0% per D.O. 29 s

    I. Value Added Tax (VAT) 0% per D.O. 29 s

    J. Total Cost

    k. Total Unit Cost

    PROJECT NAME:

    Item No./Description: Scaffolding Works

    Unit of Measurement:

    Output per day: cu.m./day

    Quantity:

    A. Labor

    a. Construction Foreman/Eng'g Assist.

    b. Skilled Laborer

    c. Laborer

    B. EquipmentN/A

    C.

    D. Output per day = cu.m. /day

    E. Materials

    a.

    b.

    c.

    F. Direct Cost (C+E)

    G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s

    Dail

    1 15 52

    0.212

    3.18 cu.m.

    Designation No. Person No. of Days

    DETAILED UNIT PRICE ANALYSIS

    PROP. CONSTRUCTION OF CONCRETE RETAINING WALL AT TAMI

    SPL-4

    cu.m.

    Name and Capacity No. of Units No. of Days Dail

    Sub-Total for A

    2 15 36

    4 15 31

    2.04589 cu.m. 8,51

    96pcs. - 2" x 3" x 10' Coco Lumber 1.13267 cu.m. 8,51

    0.212

    Name and Specifications Quantity Unit Uni

    Sub-Total for B

    Total (A+B)

    130pcs. - 2" x 4" x 10' Coco Lumber

    4" C.W. Nail 36 kgs. 70

    Sub-Total for E

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    16/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    17/61

    I. Value Added Tax (VAT) 0% per D.O. 29 s

    J. Total Cost

    k. Total Unit Cost

    PROJECT NAME:

    Item No./Description: Interlink Works

    Unit of Measurement:

    Output per day: sq.m. /day

    Quantity:

    A. Labor

    a. Construction Foreman

    b. Skilled Laborer

    c. Laborer

    B. Equipment

    a. Welding Machine w/ complete accs.

    C.

    D. Output per day = sq.m. /day

    E. Materials

    a.

    b.

    c.

    d.

    1 4 52

    3 4 36

    Designation No. Person No. of Days Dail

    DETAILED UNIT PRICE ANALYSIS

    PROP. CONSTRUCTION OF CONCRETE RETAINING WALL AT TAMI

    SPL-6

    sq.m.

    20.85

    75.33 sq.m.

    Name and Capacity No. of Units No. of Days Dail

    1 1 3,1

    Sub-Total for A

    2 4 31

    Name and Specifications Quantity Unit Uni

    10mm.x 6.00m. Plain Round Bar 39 pcs. 20

    Sub-Total for B

    Total (A+B)

    20.85

    #10 x 1.20m. x 10.00m./roll, w/50mm. x 9 rolls 1,6

    Hacksaw Blade 2 pcs. 6

    4mm. Thk. x 25mm. x 25mm. x 6.00m. 14 pcs. 35

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    18/61

    e.

    f.

    F. Direct Cost (C+E)

    G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s

    H. Contractor's Profit (CP) 10% per D.O. 29 s

    I. Value Added Tax (VAT) 12% per D.O. 29 s

    J. Total Cost

    k. Total Unit Cost

    PROJECT NAME:

    Item No./Description: Slope Protection

    Unit of Measurement:

    Output per day: cu.m./day

    Quantity:

    A. Labor a. Construction Foreman

    b. Skilled Laborer

    c. Laborer

    B. Equipment

    a. One Concrete Bagger Mixer

    C.

    D. Output per day = cu.m. /day

    E. Materials

    Sub-Total for E

    2" C.W. Nail 1 kg. 6

    6011 Welding Rod 0.5 kg. 14

    53.10 cu.m.

    Designation No. Person No. of Days Dail

    DETAILED UNIT PRICE ANALYSIS

    PROP. CONSTRUCTION OF CONCRETE RETAINING WALL AT TAMI

    SPL-7

    cu.m.

    3.54

    Sub-Total for A

    4 15 36

    8 15 31

    1 15 52

    3.54

    Name and Specifications Quantity Unit Uni

    Sub-Total for B

    Total (A+B)

    Name and Capacity No. of Units No. of Days Dail

    1 15 1,3

    1. Base Foundation

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    19/61

    F. Direct Cost (C+E)

    G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s

    H. Contractor's Profit (CP) 10% per D.O. 29 s

    I. Value Added Tax (VAT) 12% per D.O. 29 s

    J. Total Cost

    k. Total Unit Cost

    PROJECT NAME:

    Item No./Description: Masonry Works

    Unit of Measurement:

    Output per day: sq.m. /day

    Quantity:

    A. Labor

    a. Construction Foreman

    b. Skilled Laborer

    c. Laborer

    Washed Sand 8 cu.m. 90

    Gravel (G-1) 16 cu.m. 90

    Portland Cement 180 bags 26

    Hacksaw Blade 4 pcs. 6

    #16 G.I. Tie-wire 3 kgs. 7

    16mm.x 6.00m. Def. Reinforcing Steel 37 pcs. 45

    100mm.Boulders 35 cu.m. 90

    Portland Cement 88 bags 26

    2. Wall

    Sub-Total for E

    Hacksaw Blade 12 pcs. 6

    #16 G.I. Tie-wire 9 kgs. 7

    Washed Sand 8 cu.m. 90

    12mm.x 6.00m. Def. Reinforcing Steel 148 pcs. 26

    Designation No. Person No. of Days Dail

    DETAILED UNIT PRICE ANALYSIS

    PROP. CONSTRUCTION OF CONCRETE RETAINING WALL AT TAMI

    SPL-8

    sq.m.

    12.95

    129.48 sq.m.

    Sub-Total for A

    2 10 31

    1 10 52

    2 10 36

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    20/61

    B. Equipment

    N/A

    C.

    D. Output per day = sq.m. /day

    E. Materials

    F. Direct Cost (C+E)

    G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s

    H. Contractor's Profit (CP) 10% per D.O. 29 s

    I. Value Added Tax (VAT) 12% per D.O. 29 s

    J. Total Cost

    k. Total Unit Cost

    PROJECT NAME:

    Item No./Description: Stair Handrail

    Name and Capacity No. of Units No. of Days Dail

    1. Laying of 100mm. Thk. Concrte Hollow Block

    100mm. X 200mm. X 400mm. CHB (NLB) 766 pcs. 1

    Sub-Total for B

    Total (A+B)

    12.95

    Name and Specifications Quantity Unit Uni

    10mm.x 6.00m. Def. Reinforcing Steel 162.8 kgs. 4

    #16 G.I. Tie-wire 2 kgs. 7

    Portland Cement 32 bags 26

    Washed Sand 3 cu.m. 90

    2. Plastering (16mm. thk. on each side)

    Hacksaw Blade 1 pc. 6

    Filling Materials 11 cu.m. 22

    Sub-Total for E

    Portland Cement 13 bags 26

    Sand (for plastering) 1 cu.m. 1,5

    DETAILED UNIT PRICE ANALYSIS

    PROP. CONSTRUCTION OF CONCRETE RETAINING WALL AT TAMI

    SPL-9

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    21/61

    Unit of Measurement:

    Output per day: ln.m. /day

    Quantity:

    A. Labor

    a. Construction Foreman

    b.

    c. Laborer

    B. Equipment

    a.b.

    C.

    D. Output per day = ln.m. /day

    E. Materials

    a.

    b.

    c.

    d.

    F. Direct Cost (C+E)

    G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s

    H. Contractor's Profit (CP) 10% per D.O. 29 s

    I. Value Added Tax (VAT) 12% per D.O. 29 s

    J. Total Cost

    k. Total Unit Cost

    PROJECT NAME:

    Designation No. Person No. of Days Dail

    ln.m.

    13.50

    54.00 ln.m.

    1 4 31

    1 4 52

    Skilled Laborer 1 4 36

    Welding Machine w/ complete accs. 1 4 3,1Angular Grinder 1 4 30

    Sub-Total for A

    Name and Capacity No. of Units No. of Days Dail

    50mm.x 6.00m. G.I. Pipe, Sch. 20 9 pcs. 2,5

    6011 Welding Rod 2 kgs. 14

    Sub-Total for B

    Total (A+B)

    13.50

    Name and Specifications Quantity Unit Uni

    Sub-Total for E

    Hacksaw Blade 2 pcs. 62

    100mm.Grinding Wheel 1 pc. 13

    DETAILED UNIT PRICE ANALYSIS

    PROP. CONSTRUCTION OF CONCRETE RETAINING WALL AT TAMI

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    22/61

    Item No./Description: Supply & Installation of Saddle Base

    Unit of Measurement:

    Output per day: set /day

    Quantity:

    A. Labor

    a. Construction Foreman

    b.

    c. Laborer

    B. Equipmenta.

    b.

    C.

    D. Output per day = set /day

    E. Materials

    a.

    b.

    c.

    d.

    e.

    f.

    g.

    h.

    F. Direct Cost (C+E)

    G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s

    H. Contractor's Profit (CP) 10% per D.O. 29 s

    1 5 52

    0.80

    4.00 set

    Designation No. Person No. of Days

    SPL-10

    set

    Sub-Total for A

    Skilled Laborer 1 5 36

    2 5 31

    Dail

    Acetylene Cutting Outfit 1 5 36

    Sub-Total for B

    Name and Capacity No. of Units No. of Days Dail

    Welding Machine w/ complete accs. 1 5 3,1

    25mm. thk. x 400mm. x 400mm. Plain Steel 4 pcs. 4,0

    Total (A+B)

    0.80

    Name and Specifications Quantity Unit Uni

    19mm.x 75mm. Head Length 300mm. 16 pcs. 21

    25mm. Thk. x 1.20m. x 2.40m. Plain Steel 3 shts. 23,6

    6011 Welding Rod 5 kgs. 14

    100mm.Grinding Wheel 8 pcs. 13

    40mm.x 250mm. Heavy Hex. Structural 4 pcs. 24

    Sub-Total for E

    Acetylene (content only) 3 cyl. 1,4

    Industrial Oxygen (content only) 6 cyl. 65

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    23/61

    I. Value Added Tax (VAT) 12% per D.O. 29 s

    J. Total Cost

    k. Total Unit Cost

    PROJECT NAME:

    Item No./Description: Painting Works

    Unit of Measurement:

    Output per day: sq.m. /day

    Quantity:

    A. Labor

    a. Construction Foreman

    b. Skilled Laborer

    c. Laborer

    B. EquipmentN/A

    C.

    D. Output per day = sq.m. /day

    E. Materials

    a.

    b.

    c.

    d.

    e.

    f.

    g.

    52

    1 5 36

    Designation No. Person No. of Days Dail

    DETAILED UNIT PRICE ANALYSIS

    PROP. CONSTRUCTION OF CONCRETE RETAINING WALL AT TAMI

    1032

    sq.m.

    7.64

    39.04 sq.m.

    Sub-Total for B

    Sub-Total for A

    Name and Capacity No. of Units No. of Days Dail

    Metal Etching Solution 1 gal. 66

    Metal Primer 4 gals. 42

    Total (A+B)

    7.64

    Name and Specifications Quantity Unit Uni

    2" Paint Brush 5 pcs. 2

    1" Paint Brush 4 pcs. 1

    Quick Dry Enamel Paint Blue 4 gals. 60

    Quick Dry Enamel Paint Aluminum 2 gals. 76

    Paint Thinner 1 gal. 39

    2 5 31

    1 5

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    24/61

    F. Direct Cost (C+E)

    G. Overhead, Contingencies & Miscellaneous 6% per D.O. 29 s

    H. Contractor's Profit (CP) 10% per D.O. 29 s

    I. Value Added Tax (VAT) 12% per D.O. 29 s

    J. Total Cost

    k. Total Unit Cost

    Sub-Total for E

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    25/61

    P

    P

    N PRODUCTION WELL

    6.00 4,392.00

    7.00 7,608.00

    Rate Amount

    4.00 3,144.00

    15,144.00

    Rate Amount

    -

    15,144.00

    Cost Amount

    5.00 17,550.00

    .00 3,978.00

    10.64 1,807.40

    10.64 3,474.30

    5.00 425.00

    .00 130.00

    10.64 1,064.34

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    26/61

    P

    011

    011

    011

    No. of Days:

    2.33333

    P

    P

    .00 140.00

    0.00 150.00

    29,271.04

    44,415.04

    -

    -

    -

    .00 135.00

    12.02

    4.00 6,288.00

    44,415.04

    44,415.04

    N PRODUCTION WELL

    Rate Amount

    Rate Amount

    06.56 124,878.72

    95,856.00

    6.00 43,920.00

    7.00 45,648.00

    124,878.72

    220,734.72

    .00

    3.00

    .00

    70.00

    163.00

    184.00

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    27/61

    P

    011 0.06 ####

    011 ####

    011 ####

    ok

    No. of Days:

    P

    1376

    P

    Cost Amount

    -

    220,734.72

    13,244.08

    -

    -

    Amount#DIV/0!

    4.00 6,812.00

    Rate

    233,978.808,356.39

    N PRODUCTION WELL

    Rate Amount

    7.04 11,844.48

    56,264.00

    7.00 49,452.00

    11,844.48

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    28/61

    P

    011 0.06 ####

    011 ####

    011 ####

    ok

    No. of Days:

    P

    1.2 5

    68,108.48

    Cost Amount

    -

    68,108.48

    4,086.51

    -

    -

    5.33

    4.00 3,144.00

    72,194.99

    72,194.99

    N PRODUCTION WELL

    6.00 4,392.00

    7.00 15,216.00

    Rate Amount

    16.00 10,579.20

    8.00 3,516.00

    12.00 5,624.00

    22,752.00

    Rate Amount

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    29/61

    P

    16mm x 6.00m Def. Reinforcing Steel Bar 449

    12mm x 7.50m Def. Reinforcing Steel Bar 120

    12mm x 6.00m Def. Reinforcing Steel Bar 491

    Hacksaw Blade 12

    #16 G.I. Tie-wire 143

    P

    011 0.06

    011

    011

    6.95

    4.5

    6.86833

    No. of Days:

    40

    .52 202,056.47

    .65 41,278.68

    19,719.20

    42,471.20

    Cost Amount

    445,342.10

    58.08

    377,662.85

    420,134.05

    25,208.04

    -

    -

    .00 10,725.00

    Rate Amount3.00

    4.00 2,096.00

    N PRODUCTION WELL

    6.00 2,928.00

    7.00 12,680.00

    .00 864.00

    .90 122,738.71

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    30/61

    P

    P

    P

    011 0.06

    011

    011

    ok

    3.927 22.4

    0.89536 22.5

    3.5343 4.42966

    No. of Days:

    96.00 36,888.00

    1,770.40

    17,704.00

    Rate Amount

    121,258.40

    Cost Amount

    103,554.40

    16.00 64,896.00

    128,533.90

    1,169.87

    -

    121,258.40

    7,275.50

    -

    -

    6.00

    N PRODUCTION WELL

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    31/61

    P

    P

    Portland Cement 1,352

    Washed Sand 57

    Gravel (G-1) 75

    75mm x 3.00m PVC Pipe, Series 1,000 8

    12mm thk x 1.20m x 2.40m Ordinary Plywood

    270pcs. - 2" x 3" x 8' Coco Lumber

    270pcs. - 2" x 3" x 8' Coco Lumber 1,080

    P

    011 0.06

    4.00 3,144.00

    7.00 15,216.00

    6.00 8,784.00

    6.00 17,568.00

    7.00 30,432.00

    0.00 51,120.00

    6.00 16,512.002.00 11,664.00

    75,144.00

    Rate Amount

    .00 51,300.00

    .00 67,500.00

    .00 351,520.00

    79,296.00

    154,440.00

    Cost Amount

    0.64 21,689.45

    .00 58,500.00

    0.64 5,482.55

    .00 4,504.00

    561,471.01

    715,911.01

    42,954.66

    .00 975.00

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    32/61

    011

    011

    ok

    0.8

    No. of Days:

    0.212

    P

    P

    130pcs. - 2" x 4" x 10' Coco Lumber 867

    96pcs. - 2" x 3" x 10' Coco Lumber 480

    4" C.W. Nail 36

    P

    011 0.06

    -

    -

    Rate Amount

    14.99

    4.00 7,860.00

    758,865.67

    5,612.91

    N PRODUCTION WELL

    Rate Amount

    37,860.00

    6.00 10,980.00

    7.00 19,020.00

    0.64 17,411.83

    0.64 9,639.75

    Cost Amount

    -

    37,860.00

    .00 2,520.00

    29,571.58

    67,431.58

    4,045.89

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    33/61

    011

    011

    1

    No. of Days:

    P

    P

    P

    011 0.06

    011

    Rate Amount

    9.00

    N PRODUCTION WELL

    -

    -

    71,477.47

    22,487.38

    33,246.00

    Rate Amount

    7.00 28,530.00

    4.00 4,716.00

    8,856.00

    42,102.00

    Cost Amount

    4.00 8,856.00

    124,452.00

    7,467.12

    -

    82,350.00

    .00 82,350.00

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    34/61

    011

    ok

    reprint

    18

    1.5

    No. of Days:

    P

    P

    -

    131,919.12

    360.43

    4.00 2,096.00

    6.00 4,392.00

    Rate Amount4.00

    N PRODUCTION WELL

    Rate Amount

    8.00 3,128.00

    9,024.00

    7.00 2,536.00

    Cost Amount

    .00 7,800.00

    3,128.00

    12,152.00

    3.00 14,967.00

    .00 124.00

    3.00 4,942.00

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    35/61

    P

    011 0.06

    011 0.1

    011 0.12

    ok

    reprint

    18

    1.5

    No. of Days:

    P

    P

    27,967.95

    .00 63.00

    3.90 71.95

    Rate

    N PRODUCTION WELL

    40,119.95

    2,407.20

    4,012.00

    5,584.70

    52,123.84

    691.94

    67,860.00

    6.00 21,960.00

    7.00 38,040.00

    Amount15.00

    4.00 7,860.00

    Cost Amount

    20,640.00

    88,500.00

    Rate Amount

    6.00 20,640.00

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    36/61

    P

    011 0.06

    011 0.1

    011 0.12

    ok

    reprint

    18

    1.5

    No. of Days:

    P

    .00 7,200.00

    .00 14,400.00

    .00 46,800.00

    .00 248.00

    .00 225.00

    .00 16,650.00

    .00 31,500.00

    .00 22,880.00

    -187,742.00

    .00 744.00

    .00 675.00

    .00 7,200.00

    .00 39,220.00

    Rate Amount

    10.00

    N PRODUCTION WELL

    276,242.00

    16,574.52

    27,624.20

    38,452.89

    358,893.61

    6,758.82

    18,900.00

    7.00 6,340.00

    .00 5,240.00

    .00 7,320.00

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    37/61

    P

    P

    011 0.06

    011 0.1

    011 0.12

    ok

    18

    Rate Amount

    .00 10,724.00

    -

    18,900.00

    Cost Amount

    .65 7,920.00

    .00 150.00

    .00 8,320.00

    .00 2,700.00

    .00 62.00

    .00 2,475.00

    -

    37,231.00

    .00 3,380.00

    0.00 1,500.00

    N PRODUCTION WELL

    56,131.00

    3,367.86

    5,613.10

    7,813.44

    72,925.40

    563.22

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    38/61

    1.5

    No. of Days:

    500

    500 1000 50

    500

    500 2000 50

    P 500

    500 4000 50

    500

    500 5000 50

    500500 6000 50

    500

    P 500

    500 8000 50

    500

    500 9000 50

    500

    500 10000 50

    500 25

    500

    P

    011 0.06

    011 0.1

    011 0.12

    ok

    reprint

    Rate Amount4.00

    7.00 1,268.00

    4.00 2,096.00

    6.00 1,464.00

    8.00 12,512.000.00 1,200.00

    4,828.00

    Rate Amount

    2.00 22,968.00

    .90 287.80

    13,712.00

    18,540.00

    Cost Amount

    23,514.30

    42,054.30

    2,523.26

    4,205.43

    5,853.96

    .00 124.00

    .50 134.50

    54,636.95

    1,011.80

    N PRODUCTION WELL

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    39/61

    18

    1.5

    No. of Days:

    500

    500 1000 50

    500

    500 2000 50

    P 500

    500 4000 50

    500

    500 5000 50500

    500 6000 50

    500

    P 500

    500 8000 50

    500

    500 9000 50

    500

    500 10000 50

    500 25

    425

    500

    P

    011 0.06

    011 0.1

    5.00

    4.00 2,620.00

    7,620.00

    6.00 1,830.00

    7.00 3,170.00

    Rate Amount

    4.00 1,820.00

    17,460.00

    Rate Amount

    8.00 15,640.00

    2.00 16,128.00

    25,080.00

    Cost Amount

    .00 3,376.00

    15.00 70,845.00

    .90 719.50

    .50 1,076.00

    .00 992.00

    126,466.50

    7,587.99

    12,646.65

    101,386.50

    0.00 4,350.00

    .00 3,900.00

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    40/61

    011 0.12

    ok

    0.3

    18

    6.933333

    1.5

    No. of Days:

    P

    P

    17,604.14

    164,305.28

    41,076.32

    4.00 2,620.00

    6.00 1,830.00

    Rate Amount5.00

    14.56

    N PRODUCTION WELL

    -

    7,620.00

    Rate Amount

    .00 667.00

    7.00 1,708.00

    7,620.00

    Cost Amount

    .00 135.00

    .00 52.00

    6.00 2,424.00

    9.00 1,538.00

    0.00 390.00

    7.00 3,170.00

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    41/61

    P

    011 0.06

    011 0.1

    011 0.12

    2,023.13

    print

    Summary

    Labor Cost #REF!

    Equipment Cost: #REF!

    Material Cost: #REF!

    OCM: #REF!

    CP: #REF!VAT: #REF!

    Mobi/Demo: #REF!

    6,914.00

    14,534.00

    872.04

    1,453.40

    2,023.13

    18,882.57

    483.67

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    42/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    43/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    44/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    45/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    46/61

    pcs. 47.51848

    pcs.

    pcs.

    pcs.

    kgs.

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    47/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    48/61

    bags 260.00

    cu.m. 1,000.00

    cu.m. 1,000.00

    pcs. 563.00

    60 shts. 975.00

    1,080 bd.ft. 20.00

    bd.ft.

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    49/61

    bd.ft.

    bd.ft.

    kgs.

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    50/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    51/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    52/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    53/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    54/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    55/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    56/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    57/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    58/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    59/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    60/61

  • 8/11/2019 Vitali Retng Wall (Dupa Format)

    61/61