irigatie proiect

download irigatie proiect

of 35

Transcript of irigatie proiect

  • 7/31/2019 irigatie proiect

    1/35

    CHAPTER 1 : REQUIREMENTS OF A MODEL SCHEME FOR FORMULATION BY

    BANKS

    1.0. GENERAL

    This document gives broad guidelines for scheme formulation by banks for

    financing of dugwells in hard rock areas. The aspects that are necessary in

    scheme formulation are groundwater availability, well design, cost estimates,

    cropping pattern, pumpset selection and scheme economics.

    2.0. WHY SCHEME FORMULATION IS NECESSARY

    It is always desirable to formulate a scheme giving the resource availability,

    physical programme and financial aspects over a fixed time frame for

    completion of the project. Scheme formulation helps in the following ways.

    Planned and sustainable development of groundwater resources.

    Proper planning and fixing of targets on area specific basis under a given time

    frame.

    Ensuring quality of lending, systematic development, assured income to the

    beneficiary, assured repayment and recycling of credit.

    Quality control of minor irrigation works and equipments for efficient and

    economic use.

    Systematic monitoring.

    Periodical review about achievements and shorfall and taking timely remedialmeasures for successful implementation of the programme.

    In view of the above NABARD recommends proper scheme formulation and its

    techno-economic appraisal by banks before extending any refinance facilities.

    3.0. SCHEME REQUIREMENTS

  • 7/31/2019 irigatie proiect

    2/35

    Scheme formulation for construction of dugwells in hard rock areas against

    bank loans requires both technical and financial details. The important items

    that should be included in a scheme for dugwells are indicated below.

    3.1. Introduction

    This should briefly give the present status of agriculture, irrigation and need for

    increasing irrigation for improving the socio-economic conditions of the area,

    location of the scheme area, its areal extent and topographical features.

    Infrastructure availability like power, roads, etc should be described here.

    3.2. Selection of Area

    Guidance of the state groundwater department should be taken to select the

    project area for minor irrigation development so that adequate groundwater

    potential is available for future development and that the area does not come

    under over-exploited or critical category. The area selected should be a

    compact block / taluka or a watershed with adequate groundwater potential,

    easy accessibility by road and adequate outlets for sale of agricultural produce.

    This information can be obtained from the state groundwater department and

    local district authorities. Brief details about the area selected and the project

    benefits should be given in the scheme.

    3.3. Soils

    The general nature of soils prevailing in the area should be indicated. These

    can be classified as sandy, loamy, clayey or black cotton, red soils etc. Soilshave a bearing on irrigation scheduling and depth of irrigation required to meet

    the water requirement of crops. Type of soils also helps to select a suitable

    cropping pattern and the fertilizer doze.

    3.4. Climate and Rainfall

  • 7/31/2019 irigatie proiect

    3/35

    Rainfall is the main source of recharge to groundwater and groundwater

    availability largely depends upon it. It also governs the supplementary irrigaion

    requirement of crops. The scheme should therefore, indicate the monsoon and

    non-monsoon rainfall as per data recorded by the India MeteorologicalDepartment (IMD). This should also give the minimum and maximum

    temperatures during different seasons.

    3.5. Hydrogeology

    The geological formations in the area, nature and types of aquifers and their

    water yielding capacity, average depth to pre-monsoon and post-monsoon

    water table and well design suitable for the area should be indicated. Theaquifers in hard rock areas suitable for tapping groundwater are generally

    weathered zones, joints, fractures etc. Their availability in depth and areal

    extent from the point of view of groundwater development may be indicated in

    the scheme. This information is available with the district geologist of the state

    groundwater department.

    3.6. Groundwater Availability

    Before any programme of groundwater development is taken up, it is essential

    to ascertain whether adequate potential is available in the blocks covered

    under the scheme. The state groundwater department estimates groundwater

    resources on a blockwise, taluka wise or watershed wise basis and also keeps a

    record of the status of groundwater development at a given period of time. The

    categorisation of blocks as dark (critical and over-exploited) , grey (semi-

    critical) and white (safe) is made on the basis of stage of groundwater

    development expressed as a ratio of draft to utilisable resources,as well as

    trend of groundwater table. For over-exploited areas it is greater than 100%,

    for dark(critical) areas it is greater than 90%, for grey (semi-critical) areas it isgreater than 70% but less than 90%, and for white (safe) areas it is less than

    70%. This information is available with the NABARD regional office and state

    groundwater department. Banks can obtain it from them.

    Since long term behaviour of water table is a manifestation of the long duration

  • 7/31/2019 irigatie proiect

    4/35

    availability of groundwater resources, it is necessary to ensure that there is no

    declining trend of water table in the area selected for the scheme. Information

    on pre-monsoon water table is also necessary to decide the depth of well and

    to ensure that the yield of well is not affected due to depletion of water table.

    Keeping these in view and for sustainability of the structure and investment,

    new well schemes should not be formulated in dark (critical and over-

    exploited) areas.

    3.7. Groundwater Quality

    Groundwater quality in the scheme area as indicated by the state groundwaterdepartment should be given. Its suitability for irrigation may be indicated in

    terms of total dissolved solids, sodium adsorption ratio etc.

    3.8. Physical Programme

    This is desirable to assess the demand for new wells in the area before

    formulating the scheme either by interaction with the farmers or the state

    agencies like DRDA, SCSTDFC, ITDA or other organisations involved ingroundwater development programme. This facilitates fixing the physical

    targets for wells and pumpsets. If the demand is more and targets assessed

    are large, the programme could be phased over 2 to 3 years instead of

    envisaging entire programme for one year. Such a phasing helps better

    monitoring and leaves scope for mid term correction wherever required.

    Normally single design of well is uniformly followed in block suitable for the

    geological formation. However , if different designs of wells are considered

    necessary for differnt geological formations, physical programme should begiven for each type of well design.

    3.9. Well Design

  • 7/31/2019 irigatie proiect

    5/35

    An optimum well design suited to local hydrogeological conditions is important

    for success of any minor irrigation scheme. The well diameter should be based

    on hydraulic conductivity of the aquifer and the well depth or thickness of the

    saturated zone available during the peak demand. At least a 2m of water

    column in summer is desirable. Guidance from the state groundwater

    department should be taken for this. The recommended well diameter anddepth should be indicated in the scheme. Unit Cost Committee constituted by

    regional office of NABARD also recommends average design of well in different

    formations. The same should be adopted.

    3.10. Well Siting

    Normally, the state ground water department provides the map or list of

    villages within the block or watershed which are ground water worthy. For

    actual siting of well, further assistance/advice could be sought from the local

    hydrogeologist of the SGD. However, Annexure I gives the broad guidelines for

    financing institutions to enable them to decide the suitability or otherwise of

    the site for new wells.

    3.11. Spacing

    In absence of any groundwater legislation, institutional agencies exercise

    technical discipline in the form of spacing between two ground water

    structures for proper and efficient development of groundwater resources.

    Spacing is determined by aquifer performance tests conducted by the state

    groundwater department. However, to avoid over-capitalisation, economic

    spacing should also be considered and higher of the two spacings adopted for

    financing of minor irrigation works under a scheme. Spacing between two

    ground water structures is recommended by the state groundwater

    department. Therefore any variation or changes in the spacing stipulated has

    to be authenticated by that department.

    3.12. Unit Cost

    Based on the average design of well in the scheme areas, unit cost of well

    should be estimated adopting district schedule of rates and the total financial

  • 7/31/2019 irigatie proiect

    6/35

    outlay of the scheme should be worked out for the physical programme

    envisaged. However, actual cost of well may vary from location to location and

    loan should be sanctioned for actual cost of well. It is important to avoid under

    financing of well that may render the investment infructuous.

    3.13. Pumpset

    Proper selection of pumpset in conformity with BIS 10804-1994 is important to

    achieve maximum output at minimum capital and operation cost. The scheme

    should give the type of pumpset (diesel / electric), requirement of horse power

    of the pumpset, size of suction / delivery pipes for the required discharge and

    operating head as per average agronomical practices and hydrogeological

    conditions in the scheme area. If site conditions require construction of a pit or

    provision of a platform in the well steining for placement of the pumpset at

    different levels , these should also be given in the scheme and its cost

    provided for. (Please refer to NABARD publication on Selection and Financing of

    Agricultural Pumpsets).

    3.14. Economics

    The economics of investment should be given in detail to justify the loan. Thescheme should also give details about subsidies, repayment schedule, rate of

    interest etc.

    3.15. Check list

    A checklist should always accompany the proposal. This would help to check at

    a glance whether or not the details or essential items of scheme formulations

    have been incorporated. A check list is given in Annexure - II.

    CHAPTER II : MODEL FOR A SCHEME OF DUGWELLS IN HARD ROCK AREAS

    1.0. INTRODUCTION

  • 7/31/2019 irigatie proiect

    7/35

    Formulation of a scheme is explained in the subsequent paragraphs taking the

    case of a model block.The scheme aims to provide financial assistance for

    construction of 150 dugwells with pumpsets to individual farmers for irrigation

    development through groundwater sources. These wells would mostly benefitsmall and marginal farmers in the area where at present irrigation facilities

    either by surface or groundwater sources are inadequate. Dugwells are the

    most suitable stuctures for the hydrogeological conditions obtaining in the area

    and would be constucted by local contractors using conventional methods.

    Infrastructural facilities like road, powerlines and extension services by the

    state government are available for successful implementation of the minor

    irrigation programme.

    2.0. SELECTION OF SCHEME AREA

    The block in the district has been selected to formulate model scheme for

    minor irrigation development. The block has a geographical area of 17,500 ha

    of which 14,000 ha are cultivable. It is located 15 km from the district

    headquarter town. It has an undulating topography and the elevation ranges

    from 300 m to 400 m above mean sea level . A canal of 9 km length with

    wetted perimeter of 2.5 m flows for about 90 days during the non-monsoon

    period. An area of 9200 ha is presently irrigated from canal and 1157 existing

    irrigation wells.

    3.0. SOILS

    Soils in the scheme area are of black cotton type and suitable for growing

    jowar, wheat, vegetables and cash crops like sugarcane and groundnut.

    4.0. CLIMATE AND RAINFALL

    The scheme area in general has a sub-humid to tropical climate. The monsoon

    season extends from mid-June to September end. About 90% of the total

    annual rainfall of 750 mm occurs during this period only. The average

    temperature and humidity are 27o C and 65% respectively. The fair weather

  • 7/31/2019 irigatie proiect

    8/35

    season extends from mid October to February during which a winter rainfall of

    about 60 mm is recorded. The temperature during the months of December

    and January comes down to about 18oC. The hot weather conditions last from

    March to mid June and are characterised by high evaporation with temperature

    going upto 36oC. The rainfall pattern varies from year to year and on an

    average there is a dry spell once in 5 years. As per IMD records, the normalannual rainfall in the area is 760 mm.

    5.0. HYDROGEOLOGY

    The area comprises of basaltic rocks with an aggregate thickness of over 100

    m. The individual basaltic lava flows vary in thickness from 10 to 15 m and are

    made up of alternating massive and vesicular units. The massive units are hard

    and compact but highly weathered upto a depth of 10 m and are jointed and

    fractured upto a depth of about 50 m. Vesicular units are generally soft and

    make upto 30% of the total thickness of individual lava flows. These individual

    flows are sometimes separated by beds of red clays. Groundwater in the

    scheme area occurs under water table conditions. The weathered and jointed

    zones in massive units and vesicular zones are the main water bearing

    formations. These aquifers are inter-connected forming a type of multi-layered

    system but show lateral and vertical variations due to heterogenity of aquifers

    which governs the well yield. Hydrogeologically, aquifers in the scheme area

    are good and are suitable for construction of dugwells. Their hydraulic

    conductivity as estimated by the state groundwater department varies from 8to 12 m/day. Dugwells in the area vary in diameter from 4 to 6 m and in depth

    from 15 to 20 m. These wells give a discharge of 4 to 6 litres per second for a

    pumping period of 4 to 6 hours per day for a draw down of 2 to 3 meters. The

    well recoups by next day.

    6.0. GROUNDWATER AVAILABILITY

    6.1. Recharge

    The state groundwater department (SGD) has estimated the available annual

    recharge by water table fluctuation and specific yield method. This includes

    recharge from monsoon rainfall and from supplementary sources like canals

    and tanks, re-cycled irrigation water, non-monsoon rainfall etc. The available

  • 7/31/2019 irigatie proiect

    9/35

    recharge as estimated by SGD in the block is given below.

    Total Annual Groundwater Recharge(ham) 4200

    Net annual groundwater availability (ham) 3780.

    After allowing for the existing and projected demand for drinking water and

    industrial use, the balance groundwater recharge available for irrigation is

    estimated at 3570 ham.

    6.2. Draft

    Irrigation by electric and diesel operated pumpsets is the common method of

    groundwater extraction in the area. The average draft of a dugwell with

    pumpset is about 1.2 ham/year. Thus the total annual groundwater draft is

    about 1326 ham and is given in Table 1 below.

    Table 1. Draft from Existing Minor Irrigation Structures

    Sr.

    No.

    MI Works

    Nos

    Unit Draft (ham)

    Gross Yearly Draft (ham)

  • 7/31/2019 irigatie proiect

    10/35

    Monsoon

    Non-monso-on

    Yearly

    1

    Dugwell

    114

    0.65

    22

    52

    74

    2

    Dugwell with pumpset

    1,043

    1.2

    376

    876

    1,252

    Total

    398

    928

    1,326

  • 7/31/2019 irigatie proiect

    11/35

    6.3. Water Balance

    Net annual Groundwater availability for future irrigation development use is

    2244 ham.

    6.4. Stage of Groundwater Development

    The stage of groundwater development is defined by ratio of existing gross

    annual groundwater draft to net annual groundwater availability and expressedas percentage. From the groundwater estimates by the state groundwater

    department, the stage of groundwater development in the block is 41%.

    Further the long term behaviour of water levels in the observation wells as

    recorded by the state groundwater department, does not show any progressive

    decline during past 10 years. Accordingly, the block is categorised as white

    (safe) and new well programme in the block is feasible.

    7.0. PHYSICAL PROGRAMME

    A programme of 150 dugwells with pumpsets is proposed under the scheme.

    The unit gross draft of a dugwell is taken as 1.2 ham per year. The gross draft

    works out to be 180 ham, against a water balance of 2244 ham. Thus the

    proposed programme in the block is feasible. The stage of groundwater

    development after financing the proposed programme would be within 70%

    and the block would remain in the white (safe) category.

    8.0. SPACING

    The spacing between two dug wells as based on aquifer performance test

    conducted by the SGD works out to be 120 m. However, spacing on economic

    considerations has also been examined. A dugwell with pumpset can irrigate

    an area of about 2 ha and thus, on economic considerations, the spacing would

  • 7/31/2019 irigatie proiect

    12/35

    be 150 m. Thus, spacing between two wells would be kept at 150 m.

    9.0. GROUNDWATER QUALITY

    As per report of the state groundwater department, groundwater in the block

    shows low values of total dissolved solids (TDS less than 700 ppm) with Sodium

    Adsorption Ratio (SAR) less than 10. The water is therefore, suitable for

    irrigation purposes.

    10.0. WELL DESIGN

    In the scheme area a saturated thickness of about 6 m is available in a well

    depth of 15 m. The water table aquifers in the weathered and jointed zones,

    vesicular units have good hydraulic conductivity and are capable of yielding

    about 5 to 6 lps. The state groundwater department has recommended a well

    of 5m diameter and 15m depth in the scheme area and the same is adopted.

    Predictably, within this depth, atleast 2 m of water column would be available

    in the wells during summer season.

    11.0. CROPPING PATTERN AND COMMAND AREA

    The crops grown in the scheme area under irrigated conditions are jowar,

    wheat, vegetables, groundnut and sugarcane. The command area of a dugwell

    varies from 1.5 to 2 ha. The well discharge can meet the crop water

    requirement for such a farm model. The cropping pattern and water

    requirement for a 1.6 ha farm model are given below in Table 2.

    Table 2. Cropping Pattern and Water Requirement

    Command Area = 1.6 ha Working Period = 4 hrs/day

  • 7/31/2019 irigatie proiect

    13/35

    Season

    Crop

    Area (ha)

    Number of Irrigations (nos)

    Irrigation Interval (days)

    Depth of Irrigation (cm)

    Kharif

    Vegetables

    0.4

    4

    20

    5

    Groundnut

    0.8

    2

    30

    7.5

    Sugarcane

  • 7/31/2019 irigatie proiect

    14/35

    0.4

    4

    15

    7.5

    1.6

    Rabi

    Jowar

    0.8

    4

    30

    7.5

    Wheat

    0.4

  • 7/31/2019 irigatie proiect

    15/35

    6

    20

    7.5

    Sugarcane

    0.4

    12

    12

    8.75

    1.6

    Summer

    Groundnut

    0.4

    10

  • 7/31/2019 irigatie proiect

    16/35

    12

    7.5

    Sugarcane

    0.4

    12

    10

    10

    0.8

    Cropping Intensity 200% Irrigation Intensity 250%

    12.0. Discharge Required

    The discharge required has been calculated from the following formula:

    Q = 28 AI

    Rt

    where, A = Crop area in ha

  • 7/31/2019 irigatie proiect

    17/35

    I = Depth of irrigation in cm

    R = Rotation period in days

    t = Working hours per day

    Q = Required discharge in lps

    The discharge required during the different crop seasons is calculated below:

    KHARIF Q = 28 ( 0.4x5 + 0.8x7.5 + 0.4x7.5 )

    20x4 30x4 15x4

    = 3.50 lps

    RABI Q = 28 ( 0.8x7.5 + 0.4x7.5 + 0.4x8.75 )

    30x4 20x4 12x4

    = 4.49 say 4.5 lps

    SUMMER Q = 28 ( 0.4x7.5 + 0.4x10 )

    12x4 10x4

  • 7/31/2019 irigatie proiect

    18/35

    = 4.55 lps

    Considering water losses at 20% (irrigation efficiency at 80%) the required

    discharge would be:

    Kharif = 4.4 lps

    Rabi = 5.6 lps

    Summer = 5.7 lps

    The discharge required during the Rabi and Summer season is 5.6 lps and 5.7

    lps respectively, say 6 lps. This can be met from the design of well proposed

    under the scheme. A discharge of 6 lps is therefore taken for selection of

    pumpset.

    13.0. PUMPSET SELECTION

    A centrifugal pumpset is suitable for installation on dugwells. This type of

    pumpset, both electric and diesel are also commonly used in the scheme area.

    The pumpset has been selected as per IS-10804-1994 keeping in view the

    discharge and the total pumping head and the pump/motor efficiencies as

    observed from the relevant tables and curves.

    13.1. Discharge Required

    The discharge required is 6 lps for a daily pumping period of 4 hrs.

    13.2. Total Pumping Head

  • 7/31/2019 irigatie proiect

    19/35

    The total pumping head to meet peak demand (5.7 lps) in summer season is

    likely to be 15.4 m (apprx) with 65 mm dia GI pipe. This includes total static

    head, friction losses in pipes, allied fittings, foot valve and offset pipe as per

    norms on suction and delivery side. The required HP of the pumpset underthese conditions works out to be 3.0. This includes 10% additional input to

    nominal pump input to take care of tolerance on pump efficiency and variation

    in duty. Accordingly, pumpsets of 3 HP are considered under the scheme.

    13.3. Pumpset Specifications

    The specifications of the electric pumpset selected for the scheme area are as

    below:

    a) Centrifugal Pump

    Total Head (H) = 16.3 m

    Discharge(Q) = 6 lps

    Efficiency (n) = 54%

    b) Piping System

    Suction/Delivery pipes = 65 mm

    Foot valve = 65 mm

    ( K = 0.8 m)

  • 7/31/2019 irigatie proiect

    20/35

    Straight length = 17 m

    of 65 mm GI pipe

    Long radius bend (65 mm) = 2 Nos.

    c) HP of pumpset (electric/diesel) = 3

    The complete pumping system would be installed as per IS 10804 - (1994).

    14.0. COST ESTIMATE

    The cost estimate for the well with suggested design is made on the basis of

    prevalent schedule of rates. The unit cost works out to Rs.37000/-. The cost

    estimate of the dugwell in the scheme area is given below in Table 3.

    Table 3. Cost Estimate of a Dugwell

    (Indicative Only)

    Dia (m): 5 Steining (m) : 0.35

    Depth (m): 15 Depth (m) : 4.5

    Type : Brick Masonry

  • 7/31/2019 irigatie proiect

    21/35

    S.N.r

    No

    Item of Work

    Qty.

    (m3)

    Rate

    (Rs/m3)

    Amount

    (Rs)

    1

    Excavation

    a. Soil and Murum (0 to 2.5 m)

    116.35

    24

    2,792.4

    b. Hard Murum (2.5 to 4.5 m)

    70.47

  • 7/31/2019 irigatie proiect

    22/35

    30

    2,114.1

    c. Soft Rock (4.5 to 6 m)

    29.44

    33

    971.52

    d. Soft Rock (6 to 7.5 m)

    29.44

    80

    2,355.2

    e. Soft Rock (7.5 to 9 m)

    29.44

    85

    2,502.4

    f. Weathered Jointed Rock

    (9 to 10.5 m)

    29.44

    85

    2,502.4

  • 7/31/2019 irigatie proiect

    23/35

    g. Hard Rock (10.5 to 12 m)

    29.44

    165

    4,857.6

    h. Hard Rock requiring blasting

    (12 m to 15 m)

    58.40

    185

    10804.0

    28,899.62

    2

    Steining

  • 7/31/2019 irigatie proiect

    24/35

    a. Lining in Cement Mortar

    (1:6) 0.35 m thick upto 4.5 m

    26.46

    201

    5,318.76

    b. Lining in Cement Mortar

    (1:6) for parapet wall of 0.90 m

    5.30

    201

    1065.30

    3

    Dewatering During Excavation

    LS

    1,500

  • 7/31/2019 irigatie proiect

    25/35

    7,884.06

    Total cost of well

    36783.68 say Rs.37000/-

    4

    Pumphouse

    2.5 m x 2.5 m x 2.1 m

    7000

    5

    Pumpset

    3 HP (electric/diesel) pumpset conforming to ISI standards including

    accessories, piping system,transportation and installation charges etc.

    15000

    The above unit cost is as approved by NABARD regional office Unit Cost

    Committee.

  • 7/31/2019 irigatie proiect

    26/35

    15.0. TOTAL Financial Outlay

    The unit cost of a dugwell with 3 HP pumpset is Rs.59000 (Rs.37000 + Rs.7000 + Rs.15000). The financial outlay of the scheme for 150 dugwells with

    pumpsets is Rs.88.50 lakhs.

    16.0. Economics

    The scheme economics is given in Annexures III and IV. It is seen therefrom

    that the net incremental income is Rs.26,870 per year and the IRR works out to

    be 49%. Thus, the scheme is considered economically viable.

    17.0. INFRASTRUCTURAL FACILITIES

    Adequate extension services are available in the scheme area. The

    beneficiaries having irrigation facilities have adopted modern cultivation

    practices. A good net work of low tension/high tension power lines exist and

    energisation of pumpsets can be expected without any delay. A sugar factoryis located in the nearby block and marketing of sugarcane produce will not be

    a problem. A market yard exists within 3 km for marketing the agricultural

    produce and there are good all weather roads for transport of agricultural

    produce.

    18.0. Supervision and Technical Guidance

    The technical officer of the sponsoring bank would look after the supervisionand implementation of the proposal and also extend technical guidance

    wherever necessary.

    19.0. Lending Norms

  • 7/31/2019 irigatie proiect

    27/35

    Majority of beneficiaries (70%) are in the small and marginal farmers category.

    20.0. Repayment Period

    For small and marginal farmers, the loan repayment period of a dugwell would

    be 11 years excluding a gestation/grace period of 23 months and for pumpset

    9 years. The beneficiary may, if he so desires, repay the loan instalment with

    interest earlier than the stipulated period. For other farmers, the loan

    repayment period would be 9 years.

    21.0. Rate of Interest

    The present (2003-04) refinance rate to the financing bank for minor irrigation

    investments is 5.50% for NE region including Sikkim, A&N Island, whereas for

    other regions, it is 5.50% and 6.25% respectively for loansizes upto Rs.

    50.000/- and above Rs. 50,000/-. The minimum down payment would be 5%.

    ANNEXURE- I

    Guidelines for Selection of Well Sites

    Broad guidelines for financing institutions to enable them to decide upon the

    suitability (or non-suitability) of the site for new wells are given below :

    Guidelines for Location of Wells :

    Areas included between two nalas near the confluence having a soil thickness

    of over 30 cm and weathered mantle of over 5 meters (A weathered mantle

    comprises of morum, loose sandy material, etc.)

  • 7/31/2019 irigatie proiect

    28/35

    2. Alluvial flats close to river or streams.

    3. Depressions in landscape having more than 30 cm of soil cover and 5

    meters depth of weathered mantle.

    4. On the banks of nalas towards the high ground provided the banks are

    not clayey.

    5. Zone of luxuriant, vegetation with leafy plants.

    6. Old courses of rivers and streams which are represented by presence ofsands and gravels.

    7. Near the sharp bends of the streams or rivers.

    8. Damp or moist areas.

    Wells should not be located in :

    1. Areas where hard rocks are exposed.

    2. Areas adjoining ridges and spurs and within about 50 meters of them.

    3. Areas with a soil cover less than 30 cm.

    4. Areas with a weathered mantle less than 5 meters in depth.

    The thinkness of the weathered mantle can be roughly determined by looking

    at existing wells in the nearby area. If no wells exist, the exposures in nalla

  • 7/31/2019 irigatie proiect

    29/35

    beds will give an indication of the depth of weathering.

    The above guidelines, if rigidly followed, would minimise the chances of failure

    of wells and ensure location of wells in the groundwater worthy areas.

    ANNEXURE-II

    CHECK LIST

    Minor Irrigation

    Groundwater Development Schemes

    (To be completed by Bank Officer forwarding the Scheme)

    Tick in boxes to signify that the relevant information has been furnished in the

    scheme.

    1. Name of scheme :

    2. Scheme location :

    3. Area - geographical area, cultivated area and area irrigated by different

    sources :

    4. IMD normal rainfall :

    5. Geological formations

    6. Present level of groundwater development giving number of wells, filter

    points, tubewells, and other structures with unit draft/year for each :

    7. Length of canal and distributories with wetted

    perimeter and number of days of running in the scheme area :

  • 7/31/2019 irigatie proiect

    30/35

    8. Soil conditions, cropping pattern and crop water requirement :

    9. Stage of groundwater development and category of block as indicated by

    NABARD :

    10. Chemical Quality of groundwater :

    11. Spacing between different types of minor irrigation works :

    12. Groundwater draft per well and total groundwater draft under the proposed

    scheme :

    13. Design of minor irrigation works :

    14. Specifications for pumping machinery, diameter of suction and delivery

    pipes, discharge, total head and HP of pumpset :

    15. Cost estimates of minor irrigation works :

    16. Area map :

    17. Yearwise physical programme and financial outlay :

    18. Availability and arrangement for procurement and distribution of material :

    19. Financial returns on investments with reference to representative size of

    holdings in different agro-climatic zones in the scheme area :

    20. Lending terms i.e. interest rate, down payment, repayment period, extent

    of subsidy, etc. :

    21. Agency providing crop loan and its adequacy :

    22. Supervision and monitoring arrangements :

    23. Technical guidance for location of wells, specifications and design,

    selection of pumpsets, etc. :

    24. Availability of extension services :

    25. Availability of power /diesel supply :

    26. Availability of seeds/fertilizers, pesticides and their distribution :

    Annexure III

    PRE-DEVELOPMENT AND POST DEVELOPMENT INCOME FOR A FARM MODEL OF

    4 ACRES (1.6 HA)

  • 7/31/2019 irigatie proiect

    31/35

    Techno-Economic Parameters

    Acres Hectare

    Culturable Command Area4 1.6

    Irrigable Command Area 4 1.6

    Cost (Rs.)

    Civil : a) dugwell 37000

    b) pump house 7000

    Mechanical : complete pumping system15000

    Total Cost (Rs.) 59000

    Margin money @ 5% 2950

    Bank Loan 56050

    Interest on bank loan 0.15

    Grace period (years) 1

    Annual equated instalments (years) 12

    Capital recovery factor for 12 years 0.184481

    Diesel charges (Rs. for 783 hrs.) 14851

    Horse Power 3

    Cost per acre (Rs) 14750

    Cost per hectare (Rs) 36875

    Land revenue (Rs./ acre) pre-dev2

    Cost of cultivation from borrowed funds0.6

  • 7/31/2019 irigatie proiect

    32/35

    Interest on borrowed funds 0.12

    Land revenue (Rs./ acre) post-dev 8

    Repairs & Maintenance

    % of civil works 0.025

    % of mechanical works 0.03

    Annexure IV

    Pre and Post-Development Income

    Sr. No. Crop Area Yield/Acre Total yield Unit Sale Total SaleCost of cultivation/Acre Total Cost of cultivation Net income

    (Acres) (Q) (Q) Price Rs. Price ( Rs.) (Rs.) (Rs.)

    (Rs.)

    (3x4) (5x6) (3x8)

    1 2 3 4 5 6 7 8 9 10

    PRE DEVELOPMENT

    KHARIF

    1 Maize 2.5 2.5 6.3 550 3438 840 2100 1338

    2 Jowar 1.5 2.5 3.8 800 3000 1260 1890 1110

    RABI

    1 Gram 1 1.5 1.5 950 1425 885 885 540

    2 Wheat1 1.5 1.5 800 1200 790 790 410

    Total 6 9063 5665 3398

    Land revenue (Rs.2/acre) 8 Net income

    (Rs.) 2737

    Interest on borrowed funds (Rs.) 653 Net

    income/acre (Rs.) 684

  • 7/31/2019 irigatie proiect

    33/35

    POST DEVELOPMENT

    KHARIF

    1 Vegetables 1 75 75 400 30000157351573514265

    2 Groundnut 2 8 16 1450 232005430 1086012340

    RABI

    1 Wheat1 12 12 800 9600 4725 4725 4875

    2 Hybrid Jowar 2 8 16 525 8400 2195 4390 4010

    Summer

    1 Groundnut 1 9.5 9.5 1450 137756750 6750 7025

    Perennial

    1 Sugarcane 1 350 350 72.5 25375140801408011295

    110350 56540 53810

    I) Net income (Rs) 53810

    II) Land Revenue (Rs) 32

    III) ST interest (Rs) 7945

    IV) Diesel charges 14851

    V) Repairs & Maintenance

    2.5% of civil works 925

    3% of Mech. works 450

    VI) Net Surplus 29607

    VII) Pre-Development net income 2737

    VIII) Net Incremental income 26870

    IX) Net Incremental income/acre 6717

  • 7/31/2019 irigatie proiect

    34/35

    X) Interest on Bank loan 10340

    XI) Avg. repayment of loan & interest

    per acre 2585

    XII) Avg. net income per acre 4132

    INTERNAL RATE OF RETURN (IRR)

    Sr. No. Particulars YEARS

    I II III IV V VI VII VIII IX X

    XI XII XIII XIV XV

    1 Investment Cost 29500295000 0 0 0 0 0

    0 0 0 0 0 0 0

    2 Replacement Cost 0 0 0 0 0 0 0 0

    0 150000 0 0 0 0

    3 Total Cost (A) 29500295000 0 0 0 0 0

    0 150000 0 0 0 0

    4 Incremental Benefit0 20152268702687026870268702687026870

    26870268702687026870268702687026870

    5 Salvage Value 0 0 0 0 0 0 0 0

    0 0 0 0 0 0 0

    6 Total Benefit 0 2015226870268702687026870268702687026870

    268702687026870268702687026870

    7 Net Benefit -29500 -9348 268702687026870268702687026870

    26870118702687026870268702687026870

  • 7/31/2019 irigatie proiect

    35/35

    8 DF @ 15% 0.87 0.756 0.658 0.572 0.497 0.432 0.376 0.327 0.284

    0.247 0.215 0.187 0.163 0.141 0.123

    9 NPV OF COST 25665223020 0 0 0 0 00 3705 0 0 0 0 0 51672

    10 NPV OF BENEFIT 0 1523517680153701335411608101038786

    7631 6637 5777 5025 4380 3789 3305 128680

    11 NPW 77007

    12 BCR 2.49

    13 IRR 49%