46 - CAIET SARCINI - Puturi Absorbante

download 46 - CAIET SARCINI - Puturi Absorbante

of 17

Transcript of 46 - CAIET SARCINI - Puturi Absorbante

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    1/17

    S C "CONSILIER CONSTRUCT"

    BUCURE{TI

    CAIET DE SARCINI

    PENTRU LUCR|RILE DE PU}URI ABSORBANTE DE

    PE

    AUTOSTRADA BUCURE{TI - CONSTAN}A

    TRONSON LEHLIU - DRAJNA

    Km 55+700 - 97+300

    1

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    2/17

    C U P R I N S

    CAP. I. GENERALITATI

    ART. 1. OBIECT SI DOMENIUL DE APLICARE

    CAP. II. DESCRIEREA OPERATIUNILOR

    ART. 2. EXECUTIA PLATFORMEI DE LUCRU

    ART. 3. EXECUTIA SAPATURII

    ART. 4. EXECUTIA UMPLUTURII DRENANTE SI A CAPACULUI

    ART. 5. EXECUTIA PEREULUI DIN PIATRA BRUTA

    ART. 6. FINISAREA SUPRAFETELOR

    CAP. III. MATERIALE UTILIZATE. CONDITII DE CALITATE

    ART. 7. PIETRIS

    ART. 8. PIATRA SPARTAART. 9. PIATRA BRUTA

    ART. 10. BOLOVANI DE RAU

    ART. 11. GEOTEXTIL

    ART. 12. TUBURI DIN BETON

    ART. 13. OTEL BETON

    ART. 14. BETON SIMPLU

    ART. 15. MORTAR M 100

    ART. 16. APA

    ART. 17. AGREGATE

    CAP. IV. VERIFICAREA CALITATII

    ART. 18. EXECUTIA PLATFORMEI DE LUCRU

    ART. 19. EXECUTIA SAPATURII SI TUBARII PUTULUI

    ART. 20. EXECUTIA UMPLUTURII DRENANTE SI A CAPACULUI

    ART. 21. EXECUTIA PEREULUI DIN PIATRA BRUTA

    ART. 22. FINISAREA SUPRAFETELOR

    CAP. V. RECEPTIA LUCRARILOR

    ART. 23. RECEPTIA PE FAZE DE EXECUTIE

    ART. 24. RECEPTIA PRELIMINARA

    ART. 25. RECEPTIA FINALA

    2

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    3/17

    CAIET DE SARCINI

    PENTRU LUCR|RILE DE PU}URI ABSORBANTE DE PE

    AUTOSTRADA BUCURE{TI - CONSTAN}A

    TRONSON LEHLIU - DRAJNA

    Km 55+700 - 97+300

    CAP. I. GENERALITATI

    ART. 1. OBIECT SI DOMENIUL DE APLICARE

    1.1.Puturile absorbante sunt necesare atunci cand evacuarea la zi a apelor meteorice nu

    se poate realiza prin rigole, santuri sau lucrari de canalizare si cand exista un strat permeabil laadancime convenabila, capabil sa primeasca cantitatile de apa meteorice colectate si sa le

    dreneze in mod natural.

    1.2.Pentru buna functionare a puturilor absorbante, trebuie ca nivelul hidrostatic maxim

    posibil al apelor subterane sa permita evacuarea apelor meteorice prin ele. In vederea realizarii

    lor, trebuie verificat daca nu este pericol de poluare a straturilor acvifere freatice. In vederea

    realizarii lor trebuie verificat daca nu exista pericolul de poluare a straturilor acvifere freatice.

    1.3.Puturile absorbante necesita o intretinere permanenta si o verificare periodica a

    conditiilor de functionare pentru a interveni la timp cu lucrarile de curatire si refacere in cazul

    colmatarii lor.

    1 1.4. Executia puturilor absorbante necesita urmatoarele operatii:

    - executia platformei de lucru;- execotia sapaturii si tubarii putului;

    - executia umpluturii drenante si a capacului;

    - executia pereului de piatra bruta;

    - finisarea suprafetelor.

    CAP. II. DESCRIEREA OPERATIUNILOR

    ART.2. EXEXCUTIA PLATFORMEI DE LUCRU

    2.1. Lucrarea realizandu-se in zona santului de scurgere, se vor amenaja platforme delucru pe jumatate din platforma drumului, inclusiv acostamentul si santul.

    2.2. Platforma de lucru peste sant se va executa dintr-un strat de balast 0-71 conform

    STAS 662-89.

    2.3. Amenajarea platformei de lucru cuprinde:

    -Trasarea si pichetarea;

    - Curatirea terenului;

    - Indepartarea stratului vegetal de pe acostament;

    - Compactarea solului;

    - Asternerea balastului cu realizarea unei pante de scurgere a apei spre margine de 4%;

    - Compactarea stratului de balast cu cilindru compactor de 100 kN si nivelarea sa.

    3

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    4/17

    ART.3. EXECUTIA SAPATURII

    3.1. Operatiunile ce trebuie avute in vedere la executia acestor puturi sunt:

    - trasarea retelei pentru executia puturilor cu materializarea axului fiecarui put

    respectandu-se reteaua indicata in proiect;

    - fixarea instalatiei de sapat pe pozitie si calarea ei;

    - realizarea sapaturii pentru putul absorbant.3.2. Sapatura pentru putul absorbant va continua minim 1 m in stratul permeabil. Daca

    in timpul executiei sapaturii se descopara instalatii subterane, lucrarile se opresc imediat si se

    procedeaza la identificarea lor si sesizarea unitatii tutelare.

    ART. 4. EXECUTIA UMPLUTURII DRENANTE SI A CAPACULUI

    4.1. Umplutura drenanta in putul absorbant este alcatuita din:

    - bolovani sau piatra bruta;

    - piatra sparta;

    - pietris;

    - material geosintetic Netesin.4.2. Fazele necesare realizarii umpluturii drenante sunt:

    - executia la baza putului pe circa 1,50 m inaltime a unei umpluturi din bolovani sau

    piatra bruta. Bolovanii sau piatra bruta se vor cobori si aseza si nu se vor arunca, de la partea

    superioara a patului;

    - executia in continuarea stratului filtrant din piatra sparta 8...40, umplutura ce se poate

    executa prin mijloace mecanice si care trebuie sa fie impanata ca sa nu apara tasari;

    - asternerea stratului de filtru geotextil peste umplutura din piatra sparta;

    - executia umpluturii din pietris in grosime de 50 cm;

    - asternerea filtrului din geotextil, iar la partea superioara, a stratului de pietris.

    4.3. Asternerea filtrului din geotextil se face astfel incat fasiile sa fie suprapuse la

    margini pe 20...30 cm. Se recomanda ca marginile fasiilor sa fie cusute mecanic, in acest caz

    suprapunerea lor putand fi de numai 2...3 cm.

    4.4. Dupa realizarea umpluturii drenante, se executa inchiderea putului cu rama si

    capac conform plansei.

    ART. 5. EXECUTIA PEREULUI DIN PIATRA BRUTA

    5.1. De o parte si de alta a putului absorbant, pe o lungime de min. 2 m, se realizeaza o

    rigola cu adancimea conform plansei de detaliu, care se pereaza.

    5.2. Fazele necesare pereului sunt:

    - Realizarea sapaturii manuale cu taluz inclinat cu panta 2...3;- Turnarea stratului de beton de 20 cm grosime si ingroparea pietrei brute in acest strat

    in vederea realizarii pereului;

    - Compactarea pereului cu maiul de mana;

    - Rostuirea petrelor din pereu cu mortar marca M 100.

    ART. 6. FINISAREA SUPRAFETELOR

    6.1. Dupa executia coloanelor se trece la finisarea suprafetei asanate cu puturi absorbante,

    finisare ce comporta urmatoarele operatiuni:

    - scoaterea stratului de balast din platforma de lucru;

    - nivelarea suprafetei;

    4

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    5/17

    -refacerea profilului transversal al drumului, in zona afectata.

    CAP. III. MATERIALE UTILIZATE. CONDITII

    DE CALITATE

    ART.7. PIETRIS

    7.1. In umplutura drenanta se foloseste pietris sort 740 mm conform STAS 662-89 cu

    granulozitate continua.

    ART.8. PIATRA SPARTA

    8.1. In umplutura drenanta se foloseste piatra sparta negeliva, sort 8...40 conform STAS

    2917-79. Se recomanda ca piatra sa fie extrasa, inaintea iernii care precede punerea ei in opera.

    8.2. Rezistenta pietrei la gelivitate se determina conform STAS 1667-76.

    ART.9.PIATRA BRUTA

    9.1. La executia umpluturii se va folosi piatra sparta provenita din roci cu structura

    omogena, compacta. Nu se admite folosirea pietrei din roci argiloase sau marnoase. Forma

    pietrei brute este neregulata, apropiata de cea paralelipipedica. Trebuie sa fie respectate

    conditiile din STAS 2917-79 cu dimensiuni maxime de 200 mm. Piatra trebuie sa fie dura,

    negeliva, fara crapaturi si zone alterate. Rezistenta pietrei la gelivitate se determina conform

    STAS 1667-76.

    ART.10. BOLOVANI DE RAU

    10.1. Trebuie sa provina din roci nealterate, negelive si omogene ca structura sicompozitie. Nu se admit bolovani din roci conglomerate si nici bolovani cu fisuri sau cu fete de

    clivaj. Trebuie sa fie respectate conditiile din SR 667:1997. Dimensiunile bolovanilor trebuie sa

    fie de max. 200 m.

    ART.11. GEOTEXTILE

    11.1. Caracteristicile geotextilului trebuie sa corespunda prevederilor ,,Normelor tehnice

    privind utilizarea geotextilelor indicativ C 227-88. Masa geotextilului va fi de cel putin 400 g/

    m2. Nu se va accepta materialul care prezinta rarituri.

    ART.12. TUBURI DIN BETON

    12.1. Tuburile din beton pot fi cu sectiune circulara avand diametrul de 1000 mm cu cep

    si buza conform STAS 816-80 ce se folosesc si pentru executia caminelor de vizitare la drenuri.

    Acestea sunt tuburi cu cep si buza fara talpa cu lungimea de 1 m.

    ART.13. OTEL BETON

    13.1. Pentru executia scarii de acces si pentru rama si capac, la punctul absorbant, se va

    folosi otelul beton OB conform STAS 438/1-89.

    ART.14. BETON SIMPLU

    5

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    6/17

    14.1. Betonul simplu clasa Bc 7,5 (B100) se foloseste pentru executarea patului pereului

    din rigola. Pentru executia capacului si placii se foloseste beton armat clasa Bc 15 (B200). La

    stabilirea compozitiei betonului se va tine seama de prevederile ,,Cod de practica pentru

    executarea lucrarilor din beton, beton armat si beton precomprimat indicativ NE 012 - 99 luand

    in considerare:

    - lucrabilitatea betonului;- dozajul minim de ciment;

    - limitele optime ale granulozitatii;

    - rezistentele minime ale betonului ce trebuiesc asigurate.

    ART.15. MORTAR M 100

    15.1. Pentru rostuirea pereului din piatra bruta, mortarul va avea dozaj de ciment tip II B-

    S 32,5 sau II A S 32,5 de 400 kg la mc de nisip. Mortarul trebuie sa fie folosit de indata dupa

    ce a fost fabricat. Orice mortar care se va usca sau sau va incepe sa faca priza trebuie sa fie

    aruncat si sa nu admita amestecarea lui cu mortar proaspat.

    ART.16. APA

    16.1. Apa utilizata la prepararea betoanelor si mortarelor trebuie sa provina din reteaua

    publica sau alta sursa dar in acest caz trebuie sa indeplineasca conditiile tehnice prevazute in

    STAS 790-84.

    ART.7. AGREGATE

    17.1. Agregatele naturale folosite la prepararea mortarului M 100 si a betonului Bc 7,5

    sunt agregate naturale:

    - nisip 0-3, 0-7;

    - pietris sau balast pentru betoane 0-31;

    17.2. Agregatele naturale trebuie sa provina din roci stabile, nealterate de aer, apa,

    inghete, sa fie inerte sa nu conduca la efecte daunatoare asupra cimentului. Trebuie ferite de

    impurificarea cu corpuri straine. Nisipul trebuie sa fie aspru la pipait.

    CAP. IV. VERIFICAREA CALITATII LUCRARILOR

    Pentru executia unei lucrari corespunzatoare din punct de vedere calitativ, pe parcursul

    executiei, este obligatoriu sa se faca verificari pe toate fazele de executie dupa cum urmeaza:

    ART. 18. EXECUTIA PLATFORMEI DE LUCRU

    18.1. Realizarea platformei de lucru se va verifica in mod continuu vizual si prin metode

    topografice, urmarindu-se zilnic stabilitatea ei, panta de scurgere a apelor, etc. Se va verifica

    calitatea balastului pus in opera si gradul de compactare realizat.

    ART.19. EXECUTIA SAPATURILOR SI TUBARII PUTULUI

    19.1. Pentru verificarea calitatii lucrarilor, se va urmari:

    -respectarea amplasamentului conform prevederilor proiectului.

    6

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    7/17

    19.2. Rezultatul verificarii pichetarii puturilor, se consemneaza intr-un proces verbal de

    lucrari ascunse, incheiat de Antreprenor si Inginer.

    - verificarea stratificatiei terenului indicata in studiu, se va realiza prin 2-3 sondaje la

    fiecare 100 m.

    19.3. In cazul devierilor sau daca stratul permeabil nu mai este localizat la adancimea

    mentionata in proiect, lucrarile de executie vor fi oprite si ve vor adopta solutii noi, cu acordul

    Inginerului.19.4. La forajele executate, se va verifica respectarea adancimii coloanelor, prin

    verificarea numarului de tuburi din beton introduse precum si infigerea acestora cel putin 1 m in

    stratul permeabil. Rezultatele respective se vor consemna in procese verbale de lucrari ascunse.

    ART. 20. EXECUTIA UMPLUTURII DRENANTE SI A CAPACULUI

    20.1. Pentru verificarea calitatii lucrarii se va urmari:

    - verificarea tipurilor si dimensiunilor agregatelor ce reprezinta umplutura drenanta:

    piatra bruta, bolovani de rau, piatra sparta, pietris;

    - respectarea intocmai a ordinii de executie a umpluturii a umpluturii drenante

    conform proiectului;

    - verificarea filtrului din geotextil folosit din punct de vedere calitativ si a

    suprapunerii marginilor necusute control care consta in:

    - identificarea produsului;

    - determinarea masei unitare;

    - determinarea caracteristicilor hidrice-permeabilitatea;

    - verificarea calitatii agregatelor care se efectueaza pe loturi aprovizionate,

    determinandu-se: granulozitatea, conditiile de filtru, corpuri straine, parti levigabile;

    - verificarea compactarii umpluturii drenante;

    - verificarea realizarii placii si capacului putului conform planselor din proiect

    (monolitizarea ramei pe tub).

    ART. 21. EXECUTIA PEREULUI DIN PIATRA BRUTA

    21.1. Pentru verificarea calitatii lucrarilor se va urmari:

    - realizarea sapaturii la cotele date in proiect;

    - respectarea taluzului de 2/3 al sapaturii;

    - realizarea patului din beton pentru pereu, care trebuie sa aiba aceeasi grosime pe

    toata suprafata si trebuie respectata clasa betonului data in proiect;

    - se va verifica daca nu au aparut tasari;

    -rostuirea pereului de cel putin 5 cm grosime;

    - realizarea pantei pereului prevazuta in proiect;

    - nivelarea rosturilor verticale si orizontale;

    - compactarea pereului .

    Toate aceste verificari se fac conform Instruciunilor tehnice pentru executarea zidariilor

    din piatra bruta C 193-79.

    ART. 22. FINISAREA SUPRAFETELOR

    22.1. Se va verifica desfiintarea platformei de lucru, curatirea si nivelarea zonei.

    7

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    8/17

    CAP. V. RECEPTIA LUCRARILOR

    Lucrarile de puturi absorbante vor fi supuse la urmatoarele receptii:

    - Receptii pe parcursul executiei ca lucrari ascunse.

    - Receptie preliminara.

    - Receptie finala.

    Art.23. RECEPTIA PE FAZE DE EXECUTIE

    23.1. Se va verifica daca partea de lucrare ce se recep]ioneaza s-a executat conform

    proiectului si a acestui caiet de sarcini si eventual a caietului de sarcini speciale. Se face de

    Inginerul lucrarii, seful de santier, seful de lot si eventual de o comisie de receptie care

    semneaza impreuna procesul verbal de receptie. Se consemneaza:

    - trasarea, sablonarea si amplasarea lucrarii;

    - calitatea materialelor folosite;

    Se incheie un proces verbal de receptie in care sint specificate remedierile necesare,

    termenul de executie al acestora si recomandari cu privire la modul de tinere sub observatie a

    tronsoanelor la care s-au constatat abateri fata de prevederile prezentului caiet de sarcini. Seconfirma posibilitatea trecerii la faza urmatoare a lucrarilor.

    23. 2. Registrul de santier cu procese verbale de receptii pe faze si dispozitiile de santier

    se vor pune la dispozitia organelor de control si a comisiilor de receptie preliminara si finala.

    Art. 24. RECEPTIA PRELIMINARA

    24.1. Receptia preliminara se face odata cu receptia preliminara a unui sector de drum

    terminat, conform normelor legale in vigoare.

    24.2. Comisia de receptie va examina lucarile fata de prevederile documentatiei tehnice

    aprobate, fata de documentatia de control si procesele verbale de receptie pe faze, intocmite in

    timpul executiei lucrarilor.

    24.3. Lucrarile nu se vor receptiona daca:

    - nu sunt realizate cotele si celelalte dimensiuni prevazute in proiect;

    - nu este respectata calitatea materialelor folosite conform prevederilor acestui caiet de

    sarcini;

    - se costata fenomene de pierderea stabilitatii etc.

    Se vor consemna defectiunile ce se constata si se va stabili modul si termenul de

    remediere.

    Art. 25. RECEPTIA FINALA

    25.1. Receptia finala va avea loc dupa expirarea perioadei de garantie si se va face cu

    respctarea prevederilor legale in vigoare precum si a prevederilor din prezentul caiet de sarcini.

    25.2. La receptia finala a lucrarilor se va consemna modul cum s-au comportat in

    perioada de garantie si daca au fost intretinute corespunzator.

    26 septembrie 2000

    8

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    9/17

    S. C. CONSILIER CONSTRUCT

    BUCHAREST

    TECHNICAL CONDITIONS

    FOR THE ABSORBENT WELLS WORKS

    ON BUCHAREST CONSTANTA AUTO-ROAD

    LEHLIU-DRAJNA ROAD SECTION

    KM 55+700 97+300

    9

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    10/17

    C O N T E N T S

    CHAPTER I. GENERALITIES

    ART. 1. OBJECT AND CONTRACTUAL TERRITORY

    CHAPTER II. DESCRIBING THE OPERATIONSART. 2. THE CARRYING OUT OF THE WORKING PLATFORM

    ART.3. THE CARRYING OUT OF THE CONSTRUCTION PIT

    ART.4. THE CARRYING OUT OF THE DRAINING BACKFILL

    AND OF THE COVER

    ART.5. THE CARRYING OUT OF THE RAW STONE RIPRAPE

    ART.6. FINISHING THE SURFACES

    CHAPTER III. MATERIALS IN USE. QUALITY CONDITIONS

    ART. 7. GRAVELART. 8. BROKEN STONE

    ART. 9. RAW STONE

    ART.10. RIVER BOULDERS

    ART.11. GEOTEXTILE

    ART.12. CONCRETE PIPES

    ART.13. CONCRETE STEEL

    ART.14. SIMPLE CONCRETE

    ART.15. M 100 MORTAR

    ART.16. WATER

    ART.17. AGGREGATES

    CHAPTER IV. TESTING THE QUALITY OF THE WORKS

    ART.18. CARRYING OUT THE WORKING PLATFORM

    ART.19. CARRYING OUT THE CONSTRUCTION PITS

    AND THE PIPING OF THE WELL

    ART.20. CARRYING OUT THE DRAINING BACKFILL

    AND THE COVER

    ART.21. CARRYING OUT THE RAW STONE RIPRAPE

    ART.22. FINISHING THE SURFACES

    CHAPTER V. THE ACCEPTANCE OF THE WORKSART.23. THE ACCEPTANCE BY CONSTRUCTION PHASES

    ART.24. THE PRELIMINARY ACCEPTANCE

    ART.25. THE FINAL ACCEPTANCE

    10

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    11/17

    TECHNICAL CONDITIONS

    FOR THE ABSORBENT WELLS WORKS

    ON BUCHAREST CONSTANTA AUTO-ROAD

    LEHLIU-DRAJNA ROAD SECTION

    KM 55+700 97+300

    CHAPTER I. GENERALITIES

    ART. 1. OBJECT AND CONTRACTUAL TERRITORY

    1.1. The absorbent wells are necessary when the current disposal of rainwater cant be

    carried out through channels, ditches or sewerage works and when there is a permeable layer at a

    suitable depth, capable to receive the collected rainwater and naturally drain it.1.2. For a good working of the absorbent wells, the maximum possible hydrostatic level

    of the underground water must allow the evacuation of rainwater through it. To accomplish that,

    it should be verified whether there is any danger of pollution of the aquiferous phreatic layers.

    1.3. The absorbent wells need permanent maintenance and periodical verifications of the

    working conditions, to intervene in time with cleaning and restoration works in the case of their

    grouting.

    1.4. The carrying out of the absorbent wells consists of the following operations:

    - the carrying out of the working platform;

    - carrying out the construction pit and piping the well;

    - carrying out the draining backfill and the cover;

    - carrying out the raw stone riprape;

    - finishing the surfaces.

    ART. 2. THE CARRYING OUT OF THE WORKING PLATFORM

    2.1. The work being carried out in the area of the run-off ditch, working platforms will be

    fitted out on half of the roads platform, including the shoulder and the ditch.

    2.2. The working platform over the ditch will be made of a 0-71 sand and gravel mixture

    layer according to STAS 662 89.

    2.3. Fitting out the working platform comprises:- the setting out;

    - cleaning the field;

    - removing the vegetal layer from the shoulder;

    - compacting the soil;

    - laying the sand and gravel mixture layer, accomplishing a 4% slope for the water to run off

    towards the side;

    - compacting the sand and gravel mixture layer with a 100 kN compacting roller and

    leveling it.

    ART.3. THE CARRYING OUT OF THE CONSTRUCTION PIT

    11

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    12/17

    3.1. The operations that must be taken into account for the carrying out of these wells are:

    - setting out the web for the carrying out of the wells, materializing the axle of each

    well, respecting the web as shown in the project;

    - fixing the digging device on position its keying;

    - carrying out the construction pit for the absorbent well.

    3.2. The construction pit for the absorbent well will continue for at least 1m in the

    permeable layer. If during the carrying out of the construction pit underground installations arediscovered, the works must stop immediately and we proceed to their identification, noticing the

    higher unit.

    ART.4. THE CARRYING OUT OF THE DRAINING BACKFILL

    AND OF THE COVER

    4.1. The draining backfill in the absorbent well is made of:

    - boulders or raw stone;

    - broken stone;

    - gravel;

    - Netesin geosynthetic material.

    4.2. The phases necessary to carry out the draining backfill are:

    - carrying out a backfill made of boulders or raw stone at the base of the well, on about

    1.50m height. The boulders or raw stone will be lowered and laid; they wont be thrown from the

    superior side of the bed;

    - consequently carrying out the filtrating layer made of 840 broken stone, backfill

    that can be carried out with mechanical means and that has to be interlarded so there would be no

    depressions;

    - laying the geotextile filtrating layer over the broken stone backfill;

    - carrying out the gravel backfill, 50cm thick;

    -laying the geotextile filter and, on the superior part, the gravel layer.

    4.3. Laying the geotextile filter is done so that the strips should be superposed on the

    sides on 2030 cm. The sides of the strips should be mechanically sown; in this case their

    superposition can be of only 23 cm.

    4.4. After carrying out the draining backfill, we proceed to the closing of the well with

    frame and lid according to the drawing.

    ART.5. THE CARRYING OUT OF THE RAW STONE RIPRAPE

    5.1. One side and the other of the absorbent well, on a length of minimum 2m, a channel

    is carried out, with its depth according to the detailed drawing; that is paving.

    5.2 The phases necessary to the riprape are:

    - carrying out the manual construction pit with a 2/3 inclined slope;

    - casting the concrete layer, 20cm thick, and burying the raw stone in this layer to carry

    out the riprape;

    - compacting the riprape with the manual tamper;

    - joining the stones in the riprape with M 100-label mortar.

    ART.6. FINISHING THE SURFACES

    12

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    13/17

    6.1. After carrying out the columns we proceed to finishing the surface that has been

    drained with absorbent wells, finishing that consists of the following operations:

    - getting the sand and gravel mixture layer out of the working platform;

    - leveling the surface;

    - restoring the transverse profile of the road, in the affected area.

    CHAPTER III. MATERIALS IN USE. QUALITY CONDITIONS

    ART. 7. GRAVEL

    7.1. In the draining backfill, we use 740mm-sort gravel acc. to STAS 662-89, with

    continuous grading.

    ART. 8. BROKEN STONE

    8.1. In the draining backfill we use are not sensitive to frost cracks broken stone, sort 8

    40, acc. to STAS 2917-79. The stone should be extracted before the winter that precedes its

    laying.

    8.2. The stones resistance to gelivity is determined acc. to STAS 1667-76.

    ART. 9. RAW STONE

    9.1. At the carrying out of the backfill we will use broken stone that comes from rocks

    with homogenous compact structure. The use of stone that comes from clayey or marly rocks is

    not allowed. The shape of the raw stone is irregular, close to the parallelipipedic one. The

    conditions in STAS 2917-79 must be followed, with maximum dimensions of 200 mm. The

    stone must be rough, are not sensitive to frost cracks, without cracks and altered areas. The

    resistance of the stone to gelivity is determined acc. to STAS 1667-76.

    ART. 10. RIVER BOULDERS

    10.1. They must come from rocks that are unaltered, wich are not sensitive to frost

    cracks, homogenous in structure and composition. No boulders that come from conglomerate

    rocks and no boulders with cracks or cleavage sides are allowed. The conditions in SR 667: 1997

    must be followed. The dimensions of the boulders must be of max. 200 mm.

    ART. 11. GEOTEXTILES

    11.1. The characteristics of the geotextile must correspond to the stipulations of theTechnical norms regarding the use of geotextiles ind. C 227 88. The mass of the geotextile

    will be of at least 400-g/ m2. No materials with rare parts will be accepted.

    ART. 12. CONCRETE PIPES

    12.1. The concrete pipes can be with a circular section, having the diameter of 1000 mm,

    with spigot and cover acc. to STAS 816-80 that are also used to carry out the manhels for drains.

    These are pipes with spigot and cover, without fange and 1m long.

    ART. 13. CONCRETE STEEL

    13

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    14/17

    13.1. To carry out the access ladder and for the frame and cover, at the absorbent point,

    OB concrete steel will be used acc. to STAS 438/1-89.

    ART. 14. SIMPLE CONCRETE

    14.1. Simple concrete class Bc 7.5 (B 100) is used to carry out the bed of the riprape in

    the ditch. To carry out the cover and the plate, Bc 15 (B 200) class reinforced concrete is used.

    When the composition of the concrete is established, the stipulations of the Practical code for

    the carrying out of works using concrete ind. NE 012-99 will be followed, taking into account:

    - the workability of the concrete;

    - the minimum cement proportion;

    - the optimum grading limits;

    - the minimum resistance of the concrete that must be ensured.

    ART. 15. M 100 MORTAR

    15.1. To join the raw stone riprape, the mortar will have a proportion of 400kg-cement

    type II B-S 32.5 or II A-S 32.5 for 1m3 of sand. The mortar must be used immediately after it is

    made. Any mortar that dries or for which the setting begins must be thrown out and its mixture

    with fresh mortar mustnt be allowed.

    ART. 16. WATER

    16.1. The water used for the preparation of concrete and mortar must come from the

    public network or another source but in this case, it must accomplish the technical conditions

    foreseen in STAS 790-84.

    ART. 17. AGGREGATES

    17.1. The natural aggregates used to prepare M 100 mortar and Bc 7.5 concrete are

    natural aggregates:

    - sand 0-3, 0-7;

    - gravel or sand and gravel mixture for concrete (0-31).

    17.2. The natural aggregates must come from stable rocks, unaltered by air, water,

    freezing; they must be inert and not lead to damaging effects on the cement. They must be kept

    from contamination with foreign bodies. The sand must be rough at touch.

    CHAPTER IV. TESTING THE QUALITY OF THE WORKS

    To accomplish a work that is suitable from the quality point of view, during the carrying

    out obligatory tests must be made for all the phases as follows:

    ART.18. CARRYING OUT THE WORKING PLATFORM

    18.1. The carrying out of the working platform will be continuously checked visually and

    by surveying methods, daily following its stability, the slope for water run-off etc. The quality of

    14

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    15/17

    the laid sand and gravel mixture will be checked, as well as the accomplished compaction

    degree.

    ART.19. CARRYING OUT THE CONSTRUCTION PITS

    AND THE PIPING OF THE WELL

    19.1. To verify the quality of the work, we will check whether the setting out is respected

    according to the stipulations of the project.

    19.2. The result of checking the laying out of the wells is written down in a report for

    hidden works made by the Contractor and the Engineer. Checking the layers of the field

    indicated in the paper will be made by 2-3 test pits for each 100m.

    19.3. In the case of deviations or if the permeable layer is no longer placed at the depth

    stipulated in the project, the carrying out of the works will be stopped and new solutions will be

    adopted, with the approval of the Engineer.

    19.4. For the carried out drillings, we check whether the depth of the columns is

    respected by checking the number of concrete tubes that have been introduced as well as their

    thrust with at least 1m into the permeable layer. The respective results will be written down inreports for hidden works.

    ART.20. CARRYING OUT THE DRAINING BACKFILL AND THE COVER

    20.1. To test the quality of the works, we will follow:

    - checking the types and dimensions of the aggregates that represent the draining

    backfill: boulders, river boulders, broken stone, gravel;

    - strictly respecting the carrying out order of the draining backfill according to the

    project;

    -

    verifying the used geotextile filter from the quality point of view and from the pointof view of superposing the unsowed edges.

    The control consists of:

    - identifying the product;

    - determining the unitary mass;

    - determining the hydric characteristics-permeability;

    - checking the quality of the aggregates, on supplied batches, determining: the grading,

    filter conditions, foreign bodies, and elutriationable parts;

    - checking the compaction of the draining backfill;

    - checking the carrying out of the plate and of the cover according to the drawings in

    the project (loamq of the frame on the pipe).

    A RRIPRAPE

    21.1. To check the quality of the work, we have to follow:

    - carrying out the construction pit at the quotas given in the project;

    - respecting the 2/3 slope of the construction pit;

    - carrying out the concrete bed for the riprape, that must have the same thickness on

    the whole surface and we must respect the concrete class given in the project;

    - tests will be made to find out whether or not there are any depressions;

    - joining the riprape for at least 5cm thickness;

    -

    accomplishing the slope of the riprape as foreseen in the project;- leveling the vertical and horizontal joints;

    15

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    16/17

    - compacting the riprape.

    All these tests are made according to the technical Instructions for carrying out raw stone

    works C193 79.

    ART.22. FINISHING THE SURFACES

    22.1. The elimination of the working platforms, cleaning and leveling the area will be

    verified.

    CHAPTER V. THE ACCEPTANCE OF THE WORKS

    The works for the absorbent wells will be subdued to the following acceptances:

    - Acceptances during construction, as hidden works.

    -Preliminary acceptance.

    - Final acceptance.

    ART. 23. ACCEPTANCE BY CONSTRUCTION PHASES

    23.1. We verify whether the accepted part of the project has been carried out according to

    the original design and to these technical conditions, eventually the special technical conditions.

    This acceptance is made by the Engineer of the project, the site manager, the batch manager and

    eventually an acceptance committee; they all sign the acceptance report. The following aspects

    are written down:

    -

    setting out, gauging and placement of the works;- the quality of the materials in use.

    An acceptance report is written down, where the necessary adjustments, their carrying

    out time limit and suggestions regarding the way of keeping under observation the road sections

    with deviations from the stipulations of these technical norms are specified. The possibility of

    passing to the next phase is confirmed.

    23.2. The site register with acceptance reports by phases and the site dispositions will be

    presented to the controlling authorities and to the preliminary and final acceptance committees.

    Art. 24. THE PRELIMINARY ACCEPTANCE

    24.1. The preliminary acceptance is carried out when a road section is preliminaryaccepted, according to the valid legal norms.

    24.2. The acceptance committee will examine the works taking into account the

    stipulations of the technical documentation, the control documentation and the reports of

    acceptance by phase, carried out during the construction of the works.

    24.3. The works wont be accepted if:

    - the foreseen quotas and the other dimensions foreseen in the project arent

    accomplished;

    - the quality of the materials in use isnt respected according to the stipulations

    of these technical conditions;

    - phenomena such as losing stability etc are noticed.

    16

  • 7/29/2019 46 - CAIET SARCINI - Puturi Absorbante

    17/17

    The desertions will be written down and the way and term of the remedy will be

    established.

    Art. 25. THE FINAL ACCEPTANCE

    25.1. The final acceptance will take place after the guarantee period expires and taking

    into account the legal stipulations in force as well as the stipulations in these technical

    conditions.

    25.2. At the final acceptance of the foundation works, their behaviour during the

    guarantee period will be registered, as well as mentioning whether they have been properly kept.

    Octomber 2, 2000

    17