S C "CONSILIER CONSTRUCT"
BUCURE{TI
CAIET DE SARCINI
PENTRU LUCR|RILE DE PU}URI ABSORBANTE DE
PE
AUTOSTRADA BUCURE{TI - CONSTAN}A
TRONSON LEHLIU - DRAJNA
Km 55+700 - 97+300
1
7/29/2019 46 - CAIET SARCINI - Puturi Absorbante
2/17
C U P R I N S
CAP. I. GENERALITATI
ART. 1. OBIECT SI DOMENIUL DE APLICARE
CAP. II. DESCRIEREA OPERATIUNILOR
ART. 2. EXECUTIA PLATFORMEI DE LUCRU
ART. 3. EXECUTIA SAPATURII
ART. 4. EXECUTIA UMPLUTURII DRENANTE SI A CAPACULUI
ART. 5. EXECUTIA PEREULUI DIN PIATRA BRUTA
ART. 6. FINISAREA SUPRAFETELOR
CAP. III. MATERIALE UTILIZATE. CONDITII DE CALITATE
ART. 7. PIETRIS
ART. 8. PIATRA SPARTAART. 9. PIATRA BRUTA
ART. 10. BOLOVANI DE RAU
ART. 11. GEOTEXTIL
ART. 12. TUBURI DIN BETON
ART. 13. OTEL BETON
ART. 14. BETON SIMPLU
ART. 15. MORTAR M 100
ART. 16. APA
ART. 17. AGREGATE
CAP. IV. VERIFICAREA CALITATII
ART. 18. EXECUTIA PLATFORMEI DE LUCRU
ART. 19. EXECUTIA SAPATURII SI TUBARII PUTULUI
ART. 20. EXECUTIA UMPLUTURII DRENANTE SI A CAPACULUI
ART. 21. EXECUTIA PEREULUI DIN PIATRA BRUTA
ART. 22. FINISAREA SUPRAFETELOR
CAP. V. RECEPTIA LUCRARILOR
ART. 23. RECEPTIA PE FAZE DE EXECUTIE
ART. 24. RECEPTIA PRELIMINARA
ART. 25. RECEPTIA FINALA
2
7/29/2019 46 - CAIET SARCINI - Puturi Absorbante
3/17
CAIET DE SARCINI
PENTRU LUCR|RILE DE PU}URI ABSORBANTE DE PE
AUTOSTRADA BUCURE{TI - CONSTAN}A
TRONSON LEHLIU - DRAJNA
Km 55+700 - 97+300
CAP. I. GENERALITATI
ART. 1. OBIECT SI DOMENIUL DE APLICARE
1.1.Puturile absorbante sunt necesare atunci cand evacuarea la zi a apelor meteorice nu
se poate realiza prin rigole, santuri sau lucrari de canalizare si cand exista un strat permeabil laadancime convenabila, capabil sa primeasca cantitatile de apa meteorice colectate si sa le
dreneze in mod natural.
1.2.Pentru buna functionare a puturilor absorbante, trebuie ca nivelul hidrostatic maxim
posibil al apelor subterane sa permita evacuarea apelor meteorice prin ele. In vederea realizarii
lor, trebuie verificat daca nu este pericol de poluare a straturilor acvifere freatice. In vederea
realizarii lor trebuie verificat daca nu exista pericolul de poluare a straturilor acvifere freatice.
1.3.Puturile absorbante necesita o intretinere permanenta si o verificare periodica a
conditiilor de functionare pentru a interveni la timp cu lucrarile de curatire si refacere in cazul
colmatarii lor.
1 1.4. Executia puturilor absorbante necesita urmatoarele operatii:
- executia platformei de lucru;- execotia sapaturii si tubarii putului;
- executia umpluturii drenante si a capacului;
- executia pereului de piatra bruta;
- finisarea suprafetelor.
CAP. II. DESCRIEREA OPERATIUNILOR
ART.2. EXEXCUTIA PLATFORMEI DE LUCRU
2.1. Lucrarea realizandu-se in zona santului de scurgere, se vor amenaja platforme delucru pe jumatate din platforma drumului, inclusiv acostamentul si santul.
2.2. Platforma de lucru peste sant se va executa dintr-un strat de balast 0-71 conform
STAS 662-89.
2.3. Amenajarea platformei de lucru cuprinde:
-Trasarea si pichetarea;
- Curatirea terenului;
- Indepartarea stratului vegetal de pe acostament;
- Compactarea solului;
- Asternerea balastului cu realizarea unei pante de scurgere a apei spre margine de 4%;
- Compactarea stratului de balast cu cilindru compactor de 100 kN si nivelarea sa.
3
7/29/2019 46 - CAIET SARCINI - Puturi Absorbante
4/17
ART.3. EXECUTIA SAPATURII
3.1. Operatiunile ce trebuie avute in vedere la executia acestor puturi sunt:
- trasarea retelei pentru executia puturilor cu materializarea axului fiecarui put
respectandu-se reteaua indicata in proiect;
- fixarea instalatiei de sapat pe pozitie si calarea ei;
- realizarea sapaturii pentru putul absorbant.3.2. Sapatura pentru putul absorbant va continua minim 1 m in stratul permeabil. Daca
in timpul executiei sapaturii se descopara instalatii subterane, lucrarile se opresc imediat si se
procedeaza la identificarea lor si sesizarea unitatii tutelare.
ART. 4. EXECUTIA UMPLUTURII DRENANTE SI A CAPACULUI
4.1. Umplutura drenanta in putul absorbant este alcatuita din:
- bolovani sau piatra bruta;
- piatra sparta;
- pietris;
- material geosintetic Netesin.4.2. Fazele necesare realizarii umpluturii drenante sunt:
- executia la baza putului pe circa 1,50 m inaltime a unei umpluturi din bolovani sau
piatra bruta. Bolovanii sau piatra bruta se vor cobori si aseza si nu se vor arunca, de la partea
superioara a patului;
- executia in continuarea stratului filtrant din piatra sparta 8...40, umplutura ce se poate
executa prin mijloace mecanice si care trebuie sa fie impanata ca sa nu apara tasari;
- asternerea stratului de filtru geotextil peste umplutura din piatra sparta;
- executia umpluturii din pietris in grosime de 50 cm;
- asternerea filtrului din geotextil, iar la partea superioara, a stratului de pietris.
4.3. Asternerea filtrului din geotextil se face astfel incat fasiile sa fie suprapuse la
margini pe 20...30 cm. Se recomanda ca marginile fasiilor sa fie cusute mecanic, in acest caz
suprapunerea lor putand fi de numai 2...3 cm.
4.4. Dupa realizarea umpluturii drenante, se executa inchiderea putului cu rama si
capac conform plansei.
ART. 5. EXECUTIA PEREULUI DIN PIATRA BRUTA
5.1. De o parte si de alta a putului absorbant, pe o lungime de min. 2 m, se realizeaza o
rigola cu adancimea conform plansei de detaliu, care se pereaza.
5.2. Fazele necesare pereului sunt:
- Realizarea sapaturii manuale cu taluz inclinat cu panta 2...3;- Turnarea stratului de beton de 20 cm grosime si ingroparea pietrei brute in acest strat
in vederea realizarii pereului;
- Compactarea pereului cu maiul de mana;
- Rostuirea petrelor din pereu cu mortar marca M 100.
ART. 6. FINISAREA SUPRAFETELOR
6.1. Dupa executia coloanelor se trece la finisarea suprafetei asanate cu puturi absorbante,
finisare ce comporta urmatoarele operatiuni:
- scoaterea stratului de balast din platforma de lucru;
- nivelarea suprafetei;
4
7/29/2019 46 - CAIET SARCINI - Puturi Absorbante
5/17
-refacerea profilului transversal al drumului, in zona afectata.
CAP. III. MATERIALE UTILIZATE. CONDITII
DE CALITATE
ART.7. PIETRIS
7.1. In umplutura drenanta se foloseste pietris sort 740 mm conform STAS 662-89 cu
granulozitate continua.
ART.8. PIATRA SPARTA
8.1. In umplutura drenanta se foloseste piatra sparta negeliva, sort 8...40 conform STAS
2917-79. Se recomanda ca piatra sa fie extrasa, inaintea iernii care precede punerea ei in opera.
8.2. Rezistenta pietrei la gelivitate se determina conform STAS 1667-76.
ART.9.PIATRA BRUTA
9.1. La executia umpluturii se va folosi piatra sparta provenita din roci cu structura
omogena, compacta. Nu se admite folosirea pietrei din roci argiloase sau marnoase. Forma
pietrei brute este neregulata, apropiata de cea paralelipipedica. Trebuie sa fie respectate
conditiile din STAS 2917-79 cu dimensiuni maxime de 200 mm. Piatra trebuie sa fie dura,
negeliva, fara crapaturi si zone alterate. Rezistenta pietrei la gelivitate se determina conform
STAS 1667-76.
ART.10. BOLOVANI DE RAU
10.1. Trebuie sa provina din roci nealterate, negelive si omogene ca structura sicompozitie. Nu se admit bolovani din roci conglomerate si nici bolovani cu fisuri sau cu fete de
clivaj. Trebuie sa fie respectate conditiile din SR 667:1997. Dimensiunile bolovanilor trebuie sa
fie de max. 200 m.
ART.11. GEOTEXTILE
11.1. Caracteristicile geotextilului trebuie sa corespunda prevederilor ,,Normelor tehnice
privind utilizarea geotextilelor indicativ C 227-88. Masa geotextilului va fi de cel putin 400 g/
m2. Nu se va accepta materialul care prezinta rarituri.
ART.12. TUBURI DIN BETON
12.1. Tuburile din beton pot fi cu sectiune circulara avand diametrul de 1000 mm cu cep
si buza conform STAS 816-80 ce se folosesc si pentru executia caminelor de vizitare la drenuri.
Acestea sunt tuburi cu cep si buza fara talpa cu lungimea de 1 m.
ART.13. OTEL BETON
13.1. Pentru executia scarii de acces si pentru rama si capac, la punctul absorbant, se va
folosi otelul beton OB conform STAS 438/1-89.
ART.14. BETON SIMPLU
5
7/29/2019 46 - CAIET SARCINI - Puturi Absorbante
6/17
14.1. Betonul simplu clasa Bc 7,5 (B100) se foloseste pentru executarea patului pereului
din rigola. Pentru executia capacului si placii se foloseste beton armat clasa Bc 15 (B200). La
stabilirea compozitiei betonului se va tine seama de prevederile ,,Cod de practica pentru
executarea lucrarilor din beton, beton armat si beton precomprimat indicativ NE 012 - 99 luand
in considerare:
- lucrabilitatea betonului;- dozajul minim de ciment;
- limitele optime ale granulozitatii;
- rezistentele minime ale betonului ce trebuiesc asigurate.
ART.15. MORTAR M 100
15.1. Pentru rostuirea pereului din piatra bruta, mortarul va avea dozaj de ciment tip II B-
S 32,5 sau II A S 32,5 de 400 kg la mc de nisip. Mortarul trebuie sa fie folosit de indata dupa
ce a fost fabricat. Orice mortar care se va usca sau sau va incepe sa faca priza trebuie sa fie
aruncat si sa nu admita amestecarea lui cu mortar proaspat.
ART.16. APA
16.1. Apa utilizata la prepararea betoanelor si mortarelor trebuie sa provina din reteaua
publica sau alta sursa dar in acest caz trebuie sa indeplineasca conditiile tehnice prevazute in
STAS 790-84.
ART.7. AGREGATE
17.1. Agregatele naturale folosite la prepararea mortarului M 100 si a betonului Bc 7,5
sunt agregate naturale:
- nisip 0-3, 0-7;
- pietris sau balast pentru betoane 0-31;
17.2. Agregatele naturale trebuie sa provina din roci stabile, nealterate de aer, apa,
inghete, sa fie inerte sa nu conduca la efecte daunatoare asupra cimentului. Trebuie ferite de
impurificarea cu corpuri straine. Nisipul trebuie sa fie aspru la pipait.
CAP. IV. VERIFICAREA CALITATII LUCRARILOR
Pentru executia unei lucrari corespunzatoare din punct de vedere calitativ, pe parcursul
executiei, este obligatoriu sa se faca verificari pe toate fazele de executie dupa cum urmeaza:
ART. 18. EXECUTIA PLATFORMEI DE LUCRU
18.1. Realizarea platformei de lucru se va verifica in mod continuu vizual si prin metode
topografice, urmarindu-se zilnic stabilitatea ei, panta de scurgere a apelor, etc. Se va verifica
calitatea balastului pus in opera si gradul de compactare realizat.
ART.19. EXECUTIA SAPATURILOR SI TUBARII PUTULUI
19.1. Pentru verificarea calitatii lucrarilor, se va urmari:
-respectarea amplasamentului conform prevederilor proiectului.
6
7/29/2019 46 - CAIET SARCINI - Puturi Absorbante
7/17
19.2. Rezultatul verificarii pichetarii puturilor, se consemneaza intr-un proces verbal de
lucrari ascunse, incheiat de Antreprenor si Inginer.
- verificarea stratificatiei terenului indicata in studiu, se va realiza prin 2-3 sondaje la
fiecare 100 m.
19.3. In cazul devierilor sau daca stratul permeabil nu mai este localizat la adancimea
mentionata in proiect, lucrarile de executie vor fi oprite si ve vor adopta solutii noi, cu acordul
Inginerului.19.4. La forajele executate, se va verifica respectarea adancimii coloanelor, prin
verificarea numarului de tuburi din beton introduse precum si infigerea acestora cel putin 1 m in
stratul permeabil. Rezultatele respective se vor consemna in procese verbale de lucrari ascunse.
ART. 20. EXECUTIA UMPLUTURII DRENANTE SI A CAPACULUI
20.1. Pentru verificarea calitatii lucrarii se va urmari:
- verificarea tipurilor si dimensiunilor agregatelor ce reprezinta umplutura drenanta:
piatra bruta, bolovani de rau, piatra sparta, pietris;
- respectarea intocmai a ordinii de executie a umpluturii a umpluturii drenante
conform proiectului;
- verificarea filtrului din geotextil folosit din punct de vedere calitativ si a
suprapunerii marginilor necusute control care consta in:
- identificarea produsului;
- determinarea masei unitare;
- determinarea caracteristicilor hidrice-permeabilitatea;
- verificarea calitatii agregatelor care se efectueaza pe loturi aprovizionate,
determinandu-se: granulozitatea, conditiile de filtru, corpuri straine, parti levigabile;
- verificarea compactarii umpluturii drenante;
- verificarea realizarii placii si capacului putului conform planselor din proiect
(monolitizarea ramei pe tub).
ART. 21. EXECUTIA PEREULUI DIN PIATRA BRUTA
21.1. Pentru verificarea calitatii lucrarilor se va urmari:
- realizarea sapaturii la cotele date in proiect;
- respectarea taluzului de 2/3 al sapaturii;
- realizarea patului din beton pentru pereu, care trebuie sa aiba aceeasi grosime pe
toata suprafata si trebuie respectata clasa betonului data in proiect;
- se va verifica daca nu au aparut tasari;
-rostuirea pereului de cel putin 5 cm grosime;
- realizarea pantei pereului prevazuta in proiect;
- nivelarea rosturilor verticale si orizontale;
- compactarea pereului .
Toate aceste verificari se fac conform Instruciunilor tehnice pentru executarea zidariilor
din piatra bruta C 193-79.
ART. 22. FINISAREA SUPRAFETELOR
22.1. Se va verifica desfiintarea platformei de lucru, curatirea si nivelarea zonei.
7
7/29/2019 46 - CAIET SARCINI - Puturi Absorbante
8/17
CAP. V. RECEPTIA LUCRARILOR
Lucrarile de puturi absorbante vor fi supuse la urmatoarele receptii:
- Receptii pe parcursul executiei ca lucrari ascunse.
- Receptie preliminara.
- Receptie finala.
Art.23. RECEPTIA PE FAZE DE EXECUTIE
23.1. Se va verifica daca partea de lucrare ce se recep]ioneaza s-a executat conform
proiectului si a acestui caiet de sarcini si eventual a caietului de sarcini speciale. Se face de
Inginerul lucrarii, seful de santier, seful de lot si eventual de o comisie de receptie care
semneaza impreuna procesul verbal de receptie. Se consemneaza:
- trasarea, sablonarea si amplasarea lucrarii;
- calitatea materialelor folosite;
Se incheie un proces verbal de receptie in care sint specificate remedierile necesare,
termenul de executie al acestora si recomandari cu privire la modul de tinere sub observatie a
tronsoanelor la care s-au constatat abateri fata de prevederile prezentului caiet de sarcini. Seconfirma posibilitatea trecerii la faza urmatoare a lucrarilor.
23. 2. Registrul de santier cu procese verbale de receptii pe faze si dispozitiile de santier
se vor pune la dispozitia organelor de control si a comisiilor de receptie preliminara si finala.
Art. 24. RECEPTIA PRELIMINARA
24.1. Receptia preliminara se face odata cu receptia preliminara a unui sector de drum
terminat, conform normelor legale in vigoare.
24.2. Comisia de receptie va examina lucarile fata de prevederile documentatiei tehnice
aprobate, fata de documentatia de control si procesele verbale de receptie pe faze, intocmite in
timpul executiei lucrarilor.
24.3. Lucrarile nu se vor receptiona daca:
- nu sunt realizate cotele si celelalte dimensiuni prevazute in proiect;
- nu este respectata calitatea materialelor folosite conform prevederilor acestui caiet de
sarcini;
- se costata fenomene de pierderea stabilitatii etc.
Se vor consemna defectiunile ce se constata si se va stabili modul si termenul de
remediere.
Art. 25. RECEPTIA FINALA
25.1. Receptia finala va avea loc dupa expirarea perioadei de garantie si se va face cu
respctarea prevederilor legale in vigoare precum si a prevederilor din prezentul caiet de sarcini.
25.2. La receptia finala a lucrarilor se va consemna modul cum s-au comportat in
perioada de garantie si daca au fost intretinute corespunzator.
26 septembrie 2000
8
7/29/2019 46 - CAIET SARCINI - Puturi Absorbante
9/17
S. C. CONSILIER CONSTRUCT
BUCHAREST
TECHNICAL CONDITIONS
FOR THE ABSORBENT WELLS WORKS
ON BUCHAREST CONSTANTA AUTO-ROAD
LEHLIU-DRAJNA ROAD SECTION
KM 55+700 97+300
9
7/29/2019 46 - CAIET SARCINI - Puturi Absorbante
10/17
C O N T E N T S
CHAPTER I. GENERALITIES
ART. 1. OBJECT AND CONTRACTUAL TERRITORY
CHAPTER II. DESCRIBING THE OPERATIONSART. 2. THE CARRYING OUT OF THE WORKING PLATFORM
ART.3. THE CARRYING OUT OF THE CONSTRUCTION PIT
ART.4. THE CARRYING OUT OF THE DRAINING BACKFILL
AND OF THE COVER
ART.5. THE CARRYING OUT OF THE RAW STONE RIPRAPE
ART.6. FINISHING THE SURFACES
CHAPTER III. MATERIALS IN USE. QUALITY CONDITIONS
ART. 7. GRAVELART. 8. BROKEN STONE
ART. 9. RAW STONE
ART.10. RIVER BOULDERS
ART.11. GEOTEXTILE
ART.12. CONCRETE PIPES
ART.13. CONCRETE STEEL
ART.14. SIMPLE CONCRETE
ART.15. M 100 MORTAR
ART.16. WATER
ART.17. AGGREGATES
CHAPTER IV. TESTING THE QUALITY OF THE WORKS
ART.18. CARRYING OUT THE WORKING PLATFORM
ART.19. CARRYING OUT THE CONSTRUCTION PITS
AND THE PIPING OF THE WELL
ART.20. CARRYING OUT THE DRAINING BACKFILL
AND THE COVER
ART.21. CARRYING OUT THE RAW STONE RIPRAPE
ART.22. FINISHING THE SURFACES
CHAPTER V. THE ACCEPTANCE OF THE WORKSART.23. THE ACCEPTANCE BY CONSTRUCTION PHASES
ART.24. THE PRELIMINARY ACCEPTANCE
ART.25. THE FINAL ACCEPTANCE
10
7/29/2019 46 - CAIET SARCINI - Puturi Absorbante
11/17
TECHNICAL CONDITIONS
FOR THE ABSORBENT WELLS WORKS
ON BUCHAREST CONSTANTA AUTO-ROAD
LEHLIU-DRAJNA ROAD SECTION
KM 55+700 97+300
CHAPTER I. GENERALITIES
ART. 1. OBJECT AND CONTRACTUAL TERRITORY
1.1. The absorbent wells are necessary when the current disposal of rainwater cant be
carried out through channels, ditches or sewerage works and when there is a permeable layer at a
suitable depth, capable to receive the collected rainwater and naturally drain it.1.2. For a good working of the absorbent wells, the maximum possible hydrostatic level
of the underground water must allow the evacuation of rainwater through it. To accomplish that,
it should be verified whether there is any danger of pollution of the aquiferous phreatic layers.
1.3. The absorbent wells need permanent maintenance and periodical verifications of the
working conditions, to intervene in time with cleaning and restoration works in the case of their
grouting.
1.4. The carrying out of the absorbent wells consists of the following operations:
- the carrying out of the working platform;
- carrying out the construction pit and piping the well;
- carrying out the draining backfill and the cover;
- carrying out the raw stone riprape;
- finishing the surfaces.
ART. 2. THE CARRYING OUT OF THE WORKING PLATFORM
2.1. The work being carried out in the area of the run-off ditch, working platforms will be
fitted out on half of the roads platform, including the shoulder and the ditch.
2.2. The working platform over the ditch will be made of a 0-71 sand and gravel mixture
layer according to STAS 662 89.
2.3. Fitting out the working platform comprises:- the setting out;
- cleaning the field;
- removing the vegetal layer from the shoulder;
- compacting the soil;
- laying the sand and gravel mixture layer, accomplishing a 4% slope for the water to run off
towards the side;
- compacting the sand and gravel mixture layer with a 100 kN compacting roller and
leveling it.
ART.3. THE CARRYING OUT OF THE CONSTRUCTION PIT
11
7/29/2019 46 - CAIET SARCINI - Puturi Absorbante
12/17
3.1. The operations that must be taken into account for the carrying out of these wells are:
- setting out the web for the carrying out of the wells, materializing the axle of each
well, respecting the web as shown in the project;
- fixing the digging device on position its keying;
- carrying out the construction pit for the absorbent well.
3.2. The construction pit for the absorbent well will continue for at least 1m in the
permeable layer. If during the carrying out of the construction pit underground installations arediscovered, the works must stop immediately and we proceed to their identification, noticing the
higher unit.
ART.4. THE CARRYING OUT OF THE DRAINING BACKFILL
AND OF THE COVER
4.1. The draining backfill in the absorbent well is made of:
- boulders or raw stone;
- broken stone;
- gravel;
- Netesin geosynthetic material.
4.2. The phases necessary to carry out the draining backfill are:
- carrying out a backfill made of boulders or raw stone at the base of the well, on about
1.50m height. The boulders or raw stone will be lowered and laid; they wont be thrown from the
superior side of the bed;
- consequently carrying out the filtrating layer made of 840 broken stone, backfill
that can be carried out with mechanical means and that has to be interlarded so there would be no
depressions;
- laying the geotextile filtrating layer over the broken stone backfill;
- carrying out the gravel backfill, 50cm thick;
-laying the geotextile filter and, on the superior part, the gravel layer.
4.3. Laying the geotextile filter is done so that the strips should be superposed on the
sides on 2030 cm. The sides of the strips should be mechanically sown; in this case their
superposition can be of only 23 cm.
4.4. After carrying out the draining backfill, we proceed to the closing of the well with
frame and lid according to the drawing.
ART.5. THE CARRYING OUT OF THE RAW STONE RIPRAPE
5.1. One side and the other of the absorbent well, on a length of minimum 2m, a channel
is carried out, with its depth according to the detailed drawing; that is paving.
5.2 The phases necessary to the riprape are:
- carrying out the manual construction pit with a 2/3 inclined slope;
- casting the concrete layer, 20cm thick, and burying the raw stone in this layer to carry
out the riprape;
- compacting the riprape with the manual tamper;
- joining the stones in the riprape with M 100-label mortar.
ART.6. FINISHING THE SURFACES
12
7/29/2019 46 - CAIET SARCINI - Puturi Absorbante
13/17
6.1. After carrying out the columns we proceed to finishing the surface that has been
drained with absorbent wells, finishing that consists of the following operations:
- getting the sand and gravel mixture layer out of the working platform;
- leveling the surface;
- restoring the transverse profile of the road, in the affected area.
CHAPTER III. MATERIALS IN USE. QUALITY CONDITIONS
ART. 7. GRAVEL
7.1. In the draining backfill, we use 740mm-sort gravel acc. to STAS 662-89, with
continuous grading.
ART. 8. BROKEN STONE
8.1. In the draining backfill we use are not sensitive to frost cracks broken stone, sort 8
40, acc. to STAS 2917-79. The stone should be extracted before the winter that precedes its
laying.
8.2. The stones resistance to gelivity is determined acc. to STAS 1667-76.
ART. 9. RAW STONE
9.1. At the carrying out of the backfill we will use broken stone that comes from rocks
with homogenous compact structure. The use of stone that comes from clayey or marly rocks is
not allowed. The shape of the raw stone is irregular, close to the parallelipipedic one. The
conditions in STAS 2917-79 must be followed, with maximum dimensions of 200 mm. The
stone must be rough, are not sensitive to frost cracks, without cracks and altered areas. The
resistance of the stone to gelivity is determined acc. to STAS 1667-76.
ART. 10. RIVER BOULDERS
10.1. They must come from rocks that are unaltered, wich are not sensitive to frost
cracks, homogenous in structure and composition. No boulders that come from conglomerate
rocks and no boulders with cracks or cleavage sides are allowed. The conditions in SR 667: 1997
must be followed. The dimensions of the boulders must be of max. 200 mm.
ART. 11. GEOTEXTILES
11.1. The characteristics of the geotextile must correspond to the stipulations of theTechnical norms regarding the use of geotextiles ind. C 227 88. The mass of the geotextile
will be of at least 400-g/ m2. No materials with rare parts will be accepted.
ART. 12. CONCRETE PIPES
12.1. The concrete pipes can be with a circular section, having the diameter of 1000 mm,
with spigot and cover acc. to STAS 816-80 that are also used to carry out the manhels for drains.
These are pipes with spigot and cover, without fange and 1m long.
ART. 13. CONCRETE STEEL
13
7/29/2019 46 - CAIET SARCINI - Puturi Absorbante
14/17
13.1. To carry out the access ladder and for the frame and cover, at the absorbent point,
OB concrete steel will be used acc. to STAS 438/1-89.
ART. 14. SIMPLE CONCRETE
14.1. Simple concrete class Bc 7.5 (B 100) is used to carry out the bed of the riprape in
the ditch. To carry out the cover and the plate, Bc 15 (B 200) class reinforced concrete is used.
When the composition of the concrete is established, the stipulations of the Practical code for
the carrying out of works using concrete ind. NE 012-99 will be followed, taking into account:
- the workability of the concrete;
- the minimum cement proportion;
- the optimum grading limits;
- the minimum resistance of the concrete that must be ensured.
ART. 15. M 100 MORTAR
15.1. To join the raw stone riprape, the mortar will have a proportion of 400kg-cement
type II B-S 32.5 or II A-S 32.5 for 1m3 of sand. The mortar must be used immediately after it is
made. Any mortar that dries or for which the setting begins must be thrown out and its mixture
with fresh mortar mustnt be allowed.
ART. 16. WATER
16.1. The water used for the preparation of concrete and mortar must come from the
public network or another source but in this case, it must accomplish the technical conditions
foreseen in STAS 790-84.
ART. 17. AGGREGATES
17.1. The natural aggregates used to prepare M 100 mortar and Bc 7.5 concrete are
natural aggregates:
- sand 0-3, 0-7;
- gravel or sand and gravel mixture for concrete (0-31).
17.2. The natural aggregates must come from stable rocks, unaltered by air, water,
freezing; they must be inert and not lead to damaging effects on the cement. They must be kept
from contamination with foreign bodies. The sand must be rough at touch.
CHAPTER IV. TESTING THE QUALITY OF THE WORKS
To accomplish a work that is suitable from the quality point of view, during the carrying
out obligatory tests must be made for all the phases as follows:
ART.18. CARRYING OUT THE WORKING PLATFORM
18.1. The carrying out of the working platform will be continuously checked visually and
by surveying methods, daily following its stability, the slope for water run-off etc. The quality of
14
7/29/2019 46 - CAIET SARCINI - Puturi Absorbante
15/17
the laid sand and gravel mixture will be checked, as well as the accomplished compaction
degree.
ART.19. CARRYING OUT THE CONSTRUCTION PITS
AND THE PIPING OF THE WELL
19.1. To verify the quality of the work, we will check whether the setting out is respected
according to the stipulations of the project.
19.2. The result of checking the laying out of the wells is written down in a report for
hidden works made by the Contractor and the Engineer. Checking the layers of the field
indicated in the paper will be made by 2-3 test pits for each 100m.
19.3. In the case of deviations or if the permeable layer is no longer placed at the depth
stipulated in the project, the carrying out of the works will be stopped and new solutions will be
adopted, with the approval of the Engineer.
19.4. For the carried out drillings, we check whether the depth of the columns is
respected by checking the number of concrete tubes that have been introduced as well as their
thrust with at least 1m into the permeable layer. The respective results will be written down inreports for hidden works.
ART.20. CARRYING OUT THE DRAINING BACKFILL AND THE COVER
20.1. To test the quality of the works, we will follow:
- checking the types and dimensions of the aggregates that represent the draining
backfill: boulders, river boulders, broken stone, gravel;
- strictly respecting the carrying out order of the draining backfill according to the
project;
-
verifying the used geotextile filter from the quality point of view and from the pointof view of superposing the unsowed edges.
The control consists of:
- identifying the product;
- determining the unitary mass;
- determining the hydric characteristics-permeability;
- checking the quality of the aggregates, on supplied batches, determining: the grading,
filter conditions, foreign bodies, and elutriationable parts;
- checking the compaction of the draining backfill;
- checking the carrying out of the plate and of the cover according to the drawings in
the project (loamq of the frame on the pipe).
A RRIPRAPE
21.1. To check the quality of the work, we have to follow:
- carrying out the construction pit at the quotas given in the project;
- respecting the 2/3 slope of the construction pit;
- carrying out the concrete bed for the riprape, that must have the same thickness on
the whole surface and we must respect the concrete class given in the project;
- tests will be made to find out whether or not there are any depressions;
- joining the riprape for at least 5cm thickness;
-
accomplishing the slope of the riprape as foreseen in the project;- leveling the vertical and horizontal joints;
15
7/29/2019 46 - CAIET SARCINI - Puturi Absorbante
16/17
- compacting the riprape.
All these tests are made according to the technical Instructions for carrying out raw stone
works C193 79.
ART.22. FINISHING THE SURFACES
22.1. The elimination of the working platforms, cleaning and leveling the area will be
verified.
CHAPTER V. THE ACCEPTANCE OF THE WORKS
The works for the absorbent wells will be subdued to the following acceptances:
- Acceptances during construction, as hidden works.
-Preliminary acceptance.
- Final acceptance.
ART. 23. ACCEPTANCE BY CONSTRUCTION PHASES
23.1. We verify whether the accepted part of the project has been carried out according to
the original design and to these technical conditions, eventually the special technical conditions.
This acceptance is made by the Engineer of the project, the site manager, the batch manager and
eventually an acceptance committee; they all sign the acceptance report. The following aspects
are written down:
-
setting out, gauging and placement of the works;- the quality of the materials in use.
An acceptance report is written down, where the necessary adjustments, their carrying
out time limit and suggestions regarding the way of keeping under observation the road sections
with deviations from the stipulations of these technical norms are specified. The possibility of
passing to the next phase is confirmed.
23.2. The site register with acceptance reports by phases and the site dispositions will be
presented to the controlling authorities and to the preliminary and final acceptance committees.
Art. 24. THE PRELIMINARY ACCEPTANCE
24.1. The preliminary acceptance is carried out when a road section is preliminaryaccepted, according to the valid legal norms.
24.2. The acceptance committee will examine the works taking into account the
stipulations of the technical documentation, the control documentation and the reports of
acceptance by phase, carried out during the construction of the works.
24.3. The works wont be accepted if:
- the foreseen quotas and the other dimensions foreseen in the project arent
accomplished;
- the quality of the materials in use isnt respected according to the stipulations
of these technical conditions;
- phenomena such as losing stability etc are noticed.
16
7/29/2019 46 - CAIET SARCINI - Puturi Absorbante
17/17
The desertions will be written down and the way and term of the remedy will be
established.
Art. 25. THE FINAL ACCEPTANCE
25.1. The final acceptance will take place after the guarantee period expires and taking
into account the legal stipulations in force as well as the stipulations in these technical
conditions.
25.2. At the final acceptance of the foundation works, their behaviour during the
guarantee period will be registered, as well as mentioning whether they have been properly kept.
Octomber 2, 2000
17